CPWD Analysis of Rates · Water Supply

Providing and laying S&S centrifugally cast (spun) iron pipes (Class LA) conforming to IS - 1536

200 mm dia pipe

Item number
18.27.4
Analysis basis
Details of cost for 10 metre
Priced inputs
2
Derived rate
3,406.85 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.27.4 Providing and laying S&S centrifugally cast (spun) iron pipes (Class LA) conforming to IS - 1536 : 200 mm dia pipe — is derived from 2 priced inputs for 10 metre and works out to ₹3,406.85 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • 200mm dia. spun iron pipes (in 5.5 m
  • lengths)
  • Weight of 1 m pipes = 47.090 Kg
  • Weight of 10m pipes 47.090x10 = 470.90
  • Kg
CodeInputUnitQuantityRate (INR)Amount (INR)
7700S&S Centrifugally (Spun) C.I. Pipe class LA 200mm diaS&S Centrifugally (Spun) C.I. Pipe class LA 200 mm diaMaterialmetre102,275.0022,750.00
Rate same as per item no 18.23 of SH: Water SupplyRate as per item 18.23Sub-analysisquintal4.71361.651,703.37
TOTAL
24,453.37
Add 1 % Water charges on “W-A”
227.50
TOTAL
24,680.87
Add GST on “X-A” (multiplying factor 0.2127)
4,887.31
TOTAL
29,568.18
Add 15% CPOH on “Y-A”
4,179.72
TOTAL
33,747.90
Add Cess @ 1% on “Z-A”
320.45
Cost of 10 metre
34,068.35
Cost of one metre
3,406.84
Say
3,406.85

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1451. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.