Skip to main content
R/DAR 2023

Providing and laying S&S centrifugally cast (spun) iron pipes (Class LA) conforming to IS - 1536

250 mm dia pipe
Item number
18.27.5
Analysis basis
10 metre
Priced inputs
2
Derived rate
₹4,639.80/ METRE
D-01/RATE ANALYSISITEM 18.27.5

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.27.5 (Providing and laying S&S centrifugally cast (spun) iron pipes (Class LA) conforming to IS - 1536 : 250 mm dia pipe) is derived from 2 priced inputs for 10 metre and works out to ₹4,639.80 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 250mm dia. spun iron pipes (in 5.5 m
  • lengths)
  • Weight of 1 m pipes = 63.450 Kg
  • Weight of 10m pipes 63.450x10 = 634.50
  • Kg
ANALYSIS OF RATES · ITEM 18.27.5DETAILS OF COST FOR 10 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7701MATS&S Centrifugally (Spun) C.I. Pipe class LA 250mm diaS&S Centrifugally (Spun) C.I. Pipe class LA 250 mm diametre103,100.0031,000.00
SUBRate same as per item no 18.23 of SH: Water SupplyRate as per item 18.23quintal6.35361.652,296.48
BUILD-UP TO RATE
TOTAL
33,296.48
Add 1 % Water charges on “W-A”
+310.00
TOTAL
33,606.48
Add GST on “X-A” (multiplying factor 0.2127)
+6,659.64
TOTAL
40,266.12
Add 15% CPOH on “Y-A”
+5,695.45
TOTAL
45,961.57
Add Cess @ 1% on “Z-A”
+436.65
Cost of 10 metre
46,398.22
Cost of one metre
4,639.82
SAY
₹4,639.80
D-02/SOURCEPRINTED PAGE 1452
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1452

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1452. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWATER SUPPLY
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.