Providing and laying S&S centrifugally cast (spun) iron pipes (Class LA) conforming to IS - 1536

150 mm dia pipe
Item number
18.27.3
Analysis basis
10 metre
Priced inputs
2
Derived rate
₹2,037.00/ METRE
D-01/RATE ANALYSISITEM 18.27.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.27.3 (Providing and laying S&S centrifugally cast (spun) iron pipes (Class LA) conforming to IS - 1536 : 150 mm dia pipe) is derived from 2 priced inputs for 10 metre and works out to ₹2,037.00 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 150mm dia. spun iron pipes (in 5.5 m
  • lengths)
  • Weight of 1 m pipes = 32.180 Kg
  • Weight of 10m pipes 32.180x10 = 321.80
  • Kg
ANALYSIS OF RATES · ITEM 18.27.3DETAILS OF COST FOR 10 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7699MATS&S Centrifugally (Spun) C.I. Pipe class LA 150mm diaS&S Centrifugally (Spun) C.I. Pipe class LA 150 mm diametre101,350.0013,500.00
SUBRate same as per item no 18.23 of SH: Water SupplyRate as per item 18.23quintal3.22361.651,164.51
BUILD-UP TO RATE
TOTAL
14,664.51
Add 1 % Water charges on “W-A”
+135.00
TOTAL
14,799.51
Add GST on “X-A” (multiplying factor 0.2127)
+2,900.16
TOTAL
17,699.67
Add 15% CPOH on “Y-A”
+2,480.27
TOTAL
20,179.94
Add Cess @ 1% on “Z-A”
+190.15
Cost of 10 metre
20,370.09
Cost of one metre
2,037.01
SAY
₹2,037.00
D-02/SOURCEPRINTED PAGE 1451
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1451

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1451. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWATER SUPPLY
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.