R/DAR 2023

Providing and laying S&S centrifugally cast (spun) iron pipes (Class LA) conforming to IS - 1536

125 mm dia pipe
Item number
18.27.2
Analysis basis
10 metre
Priced inputs
2
Derived rate
₹1,729.35/ METRE
D-01/RATE ANALYSISITEM 18.27.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.27.2 (Providing and laying S&S centrifugally cast (spun) iron pipes (Class LA) conforming to IS - 1536 : 125 mm dia pipe) is derived from 2 priced inputs for 10 metre and works out to ₹1,729.35 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 125mm dia. spun iron pipes (in 5.5 m
  • lengths)
  • Weight of 1 m pipes = 25.820 Kg
  • Weight of 10m pipes 25.820x10 = 258.20
  • Kg
ANALYSIS OF RATES · ITEM 18.27.2DETAILS OF COST FOR 10 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7698MATS&S Centrifugally (Spun) C.I. Pipe class LA 125mm diaS&S Centrifugally (Spun) C.I. Pipe class LA 125 mm diametre101,150.0011,500.00
SUBRate same as per item no 18.23 of SH: Water SupplyRate as per item 18.23quintal2.58361.65933.06
BUILD-UP TO RATE
TOTAL
12,433.06
Add 1 % Water charges on “W-A”
+115.00
TOTAL
12,548.06
Add GST on “X-A” (multiplying factor 0.2127)
+2,470.51
TOTAL
15,018.57
Add 15% CPOH on “Y-A”
+2,112.83
TOTAL
17,131.40
Add Cess @ 1% on “Z-A”
+161.98
Cost of 10 metre
17,293.38
Cost of one metre
1,729.34
SAY
₹1,729.35
D-02/SOURCEPRINTED PAGE 1450
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1450

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1450. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.