CPWD Analysis of Rates · Water Supply

Providing and laying S&S centrifugally cast (spun) iron pipes (Class LA) conforming to IS - 1536

100 mm dia pipe

Item number
18.27.1
Analysis basis
Details of cost for 10 metre
Priced inputs
2
Derived rate
1,423.10 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.27.1 Providing and laying S&S centrifugally cast (spun) iron pipes (Class LA) conforming to IS - 1536 : 100 mm dia pipe — is derived from 2 priced inputs for 10 metre and works out to ₹1,423.10 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • 100mm dia. spun iron pipes (in 5.5 m
  • lengths)
  • Weight of 1 m pipes = 19.820 Kg
  • Weight of 10m pipes 19.820x10 = 198.20
  • Kg
CodeInputUnitQuantityRate (INR)Amount (INR)
7697S&S Centrifugally (Spun) C.I. Pipe class LA 100mm diaS&S Centrifugally (Spun) C.I. Pipe class LA 100 mm diaMaterialmetre10950.009,500.00
Rate same as per item no 18.23 of SH: Water SupplyRate as per item 18.23Sub-analysisquintal1.98361.65716.07
TOTAL
10,216.07
Add 1 % Water charges on “W-A”
95.00
TOTAL
10,311.07
Add GST on “X-A” (multiplying factor 0.2127)
2,040.86
TOTAL
12,351.93
Add 15% CPOH on “Y-A”
1,745.38
TOTAL
14,097.31
Add Cess @ 1% on “Z-A”
133.81
Cost of 10 metre
14,231.12
Cost of one metre
1,423.11
Say
1,423.10

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1450. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works