Providing and laying flanged C.I. standard specials such as tees, bends, collars, tapers, caps etc., suitable for flanged jointing as per IS : 1538

Over 300 mm dia
Item number
18.26.2
Analysis basis
1 quintal
Priced inputs
2
Derived rate
₹8,486.35/ QUINTAL
D-01/RATE ANALYSISITEM 18.26.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.26.2 (Providing and laying flanged C.I. standard specials such as tees, bends, collars, tapers, caps etc., suitable for flanged jointing as per IS : 1538 : Over 300 mm dia) is derived from 2 priced inputs for 1 quintal and works out to ₹8,486.35 per quintal after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 18.26.2DETAILS OF COST FOR 1 QUINTAL
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1470MATFlanged C.I. standard specials over 300 mm dia(heavy class)Flanged C.I. standard specials over 300 mm dia (heavy class)quintal15,500.005,500.00
SUBRate as per item No. 18.24 of SH: Water SupplyRate as per item 18.24quintal1661.85661.85
BUILD-UP TO RATE
TOTAL
6,161.85
Add 1 % Water charges on “W-A”
+55.00
TOTAL
6,216.85
Add GST on “X-A” (multiplying factor 0.2127)
+1,181.55
TOTAL
7,398.40
Add 15% CPOH on “Y-A”
+1,010.48
TOTAL
8,408.88
Add Cess @ 1% on “Z-A”
+77.47
Cost of one quintal
8,486.35
SAY
₹8,486.35
D-02/SOURCEPRINTED PAGE 1450
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1450

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1450. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWATER SUPPLY
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.