Providing and laying flanged C.I. standard specials such as tees, bends, collars, tapers, caps etc., suitable for flanged jointing as per IS : 1538
- Item number
- 18.26.2
- Analysis basis
- 1 quintal
- Priced inputs
- 2
- Derived rate
- ₹8,486.35/ QUINTAL
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.26.2 (Providing and laying flanged C.I. standard specials such as tees, bends, collars, tapers, caps etc., suitable for flanged jointing as per IS : 1538 : Over 300 mm dia) is derived from 2 priced inputs for 1 quintal and works out to ₹8,486.35 per quintal after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 1470 | MAT | Flanged C.I. standard specials over 300 mm dia(heavy class)Flanged C.I. standard specials over 300 mm dia (heavy class) | quintal | 1 | 5,500.00 | 5,500.00 |
| SUB | Rate as per item No. 18.24 of SH: Water SupplyRate as per item 18.24 | quintal | 1 | 661.85 | 661.85 |
- TOTAL
- 6,161.85
- Add 1 % Water charges on “W-A”
- +55.00
- TOTAL
- 6,216.85
- Add GST on “X-A” (multiplying factor 0.2127)
- +1,181.55
- TOTAL
- 7,398.40
- Add 15% CPOH on “Y-A”
- +1,010.48
- TOTAL
- 8,408.88
- Add Cess @ 1% on “Z-A”
- +77.47
- Cost of one quintal
- 8,486.35
- SAY
- ₹8,486.35
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1450
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1450. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.