Skip to main content
R/DAR 2023

Providing and fixing brass ferrule with C.I. mouth cover including boring and tapping the main

20 mm nominal bore
Item number
18.20.2
Analysis basis
one no
Priced inputs
2
Derived rate
₹380.00/ ONE NO
D-01/RATE ANALYSISITEM 18.20.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.20.2 (Providing and fixing brass ferrule with C.I. mouth cover including boring and tapping the main : 20 mm nominal bore) is derived from 2 priced inputs for one no and works out to ₹380.00 per one no after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 18.20.2DETAILS OF COST FOR ONE NO
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1361MATC.I.mouth, brass ferrule 20 mm diaC.I. mouth, brass ferrule 20 mm diaeach1160.00160.00
9988MATCarriage of materials and fixing chargesL.S.47.192.27107.12
BUILD-UP TO RATE
TOTAL
267.12
Add 1 % Water charges on “W”
+2.67
TOTAL
269.79
Add GST on “X” (multiplying factor 0.2127)
+57.38
TOTAL
327.17
Add 15% CPOH on “Y”
+49.08
TOTAL
376.25
Add Cess @ 1% on “Z”
+3.76
Cost of one no.
380.01
SAY
₹380.00
D-02/SOURCEPRINTED PAGE 1445
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1445

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1445. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWATER SUPPLY
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.