Providing and fixing brass ferrule with C.I. mouth cover including boring and tapping the main

25 mm nominal bore
Item number
18.20.3
Analysis basis
one no
Priced inputs
2
Derived rate
₹486.80/ ONE NO
D-01/RATE ANALYSISITEM 18.20.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.20.3 (Providing and fixing brass ferrule with C.I. mouth cover including boring and tapping the main : 25 mm nominal bore) is derived from 2 priced inputs for one no and works out to ₹486.80 per one no after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 18.20.3DETAILS OF COST FOR ONE NO
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1362MATC.I.mouth, brass ferrule 25 mm diaC.l. mouth, brass ferrule 25 mm diaeach1220.00220.00
9988MATCarriage of materials and fixing chargesL.S.53.822.27122.17
BUILD-UP TO RATE
TOTAL
342.17
Add 1 % Water charges on “W”
+3.42
TOTAL
345.59
Add GST on “X” (multiplying factor 0.2127)
+73.51
TOTAL
419.10
Add 15% CPOH on “Y”
+62.87
TOTAL
481.97
Add Cess @ 1% on “Z”
+4.82
Cost of one no.
486.79
SAY
₹486.80
D-02/SOURCEPRINTED PAGE 1445
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1445

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1445. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.