CPWD Analysis of Rates · Water Supply

Providing and fixing brass ferrule with C.I. mouth cover including boring and tapping the main

15 mm nominal bore

Item number
18.20.1
Analysis basis
Details of cost for one no.
Priced inputs
2
Derived rate
329.30 / one no

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.20.1 Providing and fixing brass ferrule with C.I. mouth cover including boring and tapping the main : 15 mm nominal bore — is derived from 2 priced inputs for one no and works out to ₹329.30 per one no after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
1360C.I.mouth, brass ferrule 15 mm diaC.I. mouth, brass ferrule 15 mm diaMaterialeach1140.00140.00
9988Carriage of materials and fixing chargesMaterialL.S.40.32.2791.48
TOTAL
231.48
Add 1 % Water charges on “W”
2.31
TOTAL
233.79
Add GST on “X” (multiplying factor 0.2127)
49.73
TOTAL
283.52
Add 15% CPOH on “Y”
42.53
TOTAL
326.05
Add Cess @ 1% on “Z”
3.26
Cost of one no.
329.31
Say
329.30

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1445. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.