R/DAR 2023

Providing and Placing in position suitable PVC water stops conforming to IS:12200 for construction/ expansion joints between two RCC members and fixed to the reinforcement with binding wire before pouring concrete etc. complete

Dumb bell with central bulb (180 mm wide, 8 mm thick)
Item number
22.4.2
Analysis basis
100 metres
Priced inputs
3
Derived rate
₹267.90/ METRES
D-01/RATE ANALYSISITEM 22.4.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 22.4.2 (Providing and Placing in position suitable PVC water stops conforming to IS:12200 for construction/ expansion joints between two RCC members and fixed to the reinforcement with binding wire before pouring concrete etc. complete : Dumb bell with central bulb (180 mm wide, 8 mm thick)) is derived from 3 priced inputs for 100 metres and works out to ₹267.90 per metres after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 22.4.2DETAILS OF COST FOR 100 METRES
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7428MATWater stops Dumb bell with central bulbmetre100173.0017,300.00
0114LABBeldarday2736.001,472.00
9999MATSundries & wire etc.L.S.262.2759.02
BUILD-UP TO RATE
TOTAL
18,831.02
Add 1 % Water charges on “W”
+188.31
TOTAL
19,019.33
Add GST on “X” (multiplying factor 0.2127)
+4,045.41
TOTAL
23,064.74
Add 15% CPOH on “Y”
+3,459.71
TOTAL
26,524.45
Add Cess @ 1% on “Z”
+265.24
Cost for 100 metres
26,789.69
Cost for 1 metre
267.90
SAY
₹267.90
D-02/SOURCEPRINTED PAGE 1848
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1848

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1848. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.