Providing and Placing in position suitable PVC water stops conforming to IS:12200 for construction/ expansion joints between two RCC members and fixed to the reinforcement with binding wire before pouring concrete etc. complete
- Item number
- 22.4.1
- Analysis basis
- 100 metres
- Priced inputs
- 3
- Derived rate
- ₹327.65/ METRES
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 22.4.1 (Providing and Placing in position suitable PVC water stops conforming to IS:12200 for construction/ expansion joints between two RCC members and fixed to the reinforcement with binding wire before pouring concrete etc. complete : Serrated with central bulb (225 mm wide, 8-11 mm thick)) is derived from 3 priced inputs for 100 metres and works out to ₹327.65 per metres after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7427 | MAT | Water stops Serrated with central bulb (225 mm wide, 8-11 mm thick) | metre | 100 | 215.00 | 21,500.00 |
| 0114 | LAB | Beldar | day | 2 | 736.00 | 1,472.00 |
| 9999 | MAT | Sundries & wire etc. | L.S. | 26 | 2.27 | 59.02 |
- TOTAL
- 23,031.02
- Add 1 % Water charges on “W”
- +230.31
- TOTAL
- 23,261.33
- Add GST on “X” (multiplying factor 0.2127)
- +4,947.68
- TOTAL
- 28,209.01
- Add 15% CPOH on “Y”
- +4,231.35
- TOTAL
- 32,440.36
- Add Cess @ 1% on “Z”
- +324.40
- Cost for 100 metres
- 32,764.76
- Cost for 1 metre
- 327.65
- SAY
- ₹327.65
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1848
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1848. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.