Providing and Placing in position suitable PVC water stops conforming to IS:12200 for construction/ expansion joints between two RCC members and fixed to the reinforcement with binding wire before pouring concrete etc. complete

Serrated with central bulb (225 mm wide, 8-11 mm thick)
Item number
22.4.1
Analysis basis
100 metres
Priced inputs
3
Derived rate
₹327.65/ METRES
D-01/RATE ANALYSISITEM 22.4.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 22.4.1 (Providing and Placing in position suitable PVC water stops conforming to IS:12200 for construction/ expansion joints between two RCC members and fixed to the reinforcement with binding wire before pouring concrete etc. complete : Serrated with central bulb (225 mm wide, 8-11 mm thick)) is derived from 3 priced inputs for 100 metres and works out to ₹327.65 per metres after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 22.4.1DETAILS OF COST FOR 100 METRES
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7427MATWater stops Serrated with central bulb (225 mm wide, 8-11 mm thick)metre100215.0021,500.00
0114LABBeldarday2736.001,472.00
9999MATSundries & wire etc.L.S.262.2759.02
BUILD-UP TO RATE
TOTAL
23,031.02
Add 1 % Water charges on “W”
+230.31
TOTAL
23,261.33
Add GST on “X” (multiplying factor 0.2127)
+4,947.68
TOTAL
28,209.01
Add 15% CPOH on “Y”
+4,231.35
TOTAL
32,440.36
Add Cess @ 1% on “Z”
+324.40
Cost for 100 metres
32,764.76
Cost for 1 metre
327.65
SAY
₹327.65
D-02/SOURCEPRINTED PAGE 1848
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1848

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1848. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.