Skip to main content

CPWD Analysis of Rates · Water Proofing

Providing and Placing in position suitable PVC water stops conforming to IS:12200 for construction/ expansion joints between two RCC members and fixed to the reinforcement with binding wire before pouring concrete etc. complete

Serrated with central bulb (225 mm wide, 8-11 mm thick)

Item number
22.4.1
Analysis basis
Details of cost for 100 metres
Priced inputs
3
Derived rate
327.65 / metres

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 22.4.1 Providing and Placing in position suitable PVC water stops conforming to IS:12200 for construction/ expansion joints between two RCC members and fixed to the reinforcement with binding wire before pouring concrete etc. complete : Serrated with central bulb (225 mm wide, 8-11 mm thick) — is derived from 3 priced inputs for 100 metres and works out to ₹327.65 per metres after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
7427Water stops Serrated with central bulb (225 mm wide, 8-11 mm thick)Materialmetre100215.0021,500.00
0114BeldarLabourday2736.001,472.00
9999Sundries & wire etc.MaterialL.S.262.2759.02
TOTAL
23,031.02
Add 1 % Water charges on “W”
230.31
TOTAL
23,261.33
Add GST on “X” (multiplying factor 0.2127)
4,947.68
TOTAL
28,209.01
Add 15% CPOH on “Y”
4,231.35
TOTAL
32,440.36
Add Cess @ 1% on “Z”
324.40
Cost for 100 metres
32,764.76
Cost for 1 metre
327.65
Say
327.65

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1848. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works