Providing and applying fibre reinforced elastomeric liquid water proofing membrane with resilient acrylic polymers having Sun Reflectivity Index (SRI) of 105 on top of concrete roof in three coats @10.76 litre/ 10 sqm. One coat of self-priming of elastomeric waterproofing liquid (dilution with water in the ratio of 3:1) and two coats of undiluted elastomeric waterproofing liquid (dry film thickness of complete application/system not less than 500 microns). The operation shall be carried out after scrapping and properly cleaning the surface to remove loose particles with wire brushes, complete in all respect as per the direction of Engineer-inCharge

Item number
22.22A
Analysis basis
10 Sqm
Priced inputs
6
Derived rate
₹563.10/ SQM
D-01/RATE ANALYSISITEM 22.22A

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 22.22A (Providing and applying fibre reinforced elastomeric liquid water proofing membrane with resilient acrylic polymers having Sun Reflectivity Index (SRI) of 105 on top of concrete roof in three coats @10.76 litre/ 10 sqm. One coat of self-priming of elastomeric waterproofing liquid (dilution with water in the ratio of 3:1) and two coats of undiluted elastomeric waterproofing liquid (dry film thickness of complete application/system not less than 500 microns). The operation shall be carried out after scrapping and properly cleaning the surface to remove loose particles with wire brushes, complete in all respect as per the direction of Engineer-inCharge) is derived from 6 priced inputs for 10 Sqm and works out to ₹563.10 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 10.76 litre + 0.538 (Add wastage 5%) = 11.30
  • litre
ANALYSIS OF RATES · ITEM 22.22ADETAILS OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8511MATFibre reinforced elastomeric liquid water proofing membranelitre11.3255.002,881.50
9977MATCarriage of materialsL.S.1.432.273.25
0115LABCoolieday0.67736.00493.12
0131LABPainterday0.67816.00546.72
9999MATWire brush brushes, rollers etc.L.S.6.762.2715.35
9999MATSundriesL.S.8.062.2718.30
BUILD-UP TO RATE
TOTAL
3,958.24
Add 1 % Water charges on “W”
+39.58
TOTAL
3,997.82
Add GST on “X” (multiplying factor 0.2127)
+850.34
TOTAL
4,848.16
Add 15% CPOH on “Y”
+727.22
TOTAL
5,575.38
Add Cess @ 1% on “Z”
+55.75
Cost of 10 sqm
5,631.13
Cost of 1 sqm
563.11
SAY
₹563.10
D-02/SOURCEPRINTED PAGE 1859
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1859

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1859. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWATER PROOFING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.