Providing and applying fibre reinforced elastomeric liquid water proofing membrane with resilient acrylic polymers having Sun Reflectivity Index (SRI) of 105 on top of concrete roof in three coats @10.76 litre/ 10 sqm. One coat of self-priming of elastomeric waterproofing liquid (dilution with water in the ratio of 3:1) and two coats of undiluted elastomeric waterproofing liquid (dry film thickness of complete application/system not less than 500 microns). The operation shall be carried out after scrapping and properly cleaning the surface to remove loose particles with wire brushes, complete in all respect as per the direction of Engineer-inCharge

Item number
22.22A
Analysis basis
Details of cost for 10 Sqm
Priced inputs
6
Derived rate
563.10 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 22.22A Providing and applying fibre reinforced elastomeric liquid water proofing membrane with resilient acrylic polymers having Sun Reflectivity Index (SRI) of 105 on top of concrete roof in three coats @10.76 litre/ 10 sqm. One coat of self-priming of elastomeric waterproofing liquid (dilution with water in the ratio of 3:1) and two coats of undiluted elastomeric waterproofing liquid (dry film thickness of complete application/system not less than 500 microns). The operation shall be carried out after scrapping and properly cleaning the surface to remove loose particles with wire brushes, complete in all respect as per the direction of Engineer-inCharge — is derived from 6 priced inputs for 10 Sqm and works out to ₹563.10 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • 10.76 litre + 0.538 (Add wastage 5%) = 11.30
  • litre
CodeInputUnitQuantityRate (INR)Amount (INR)
8511Fibre reinforced elastomeric liquid water proofing membraneMateriallitre11.3255.002,881.50
9977Carriage of materialsMaterialL.S.1.432.273.25
0115CoolieLabourday0.67736.00493.12
0131PainterLabourday0.67816.00546.72
9999Wire brush brushes, rollers etc.MaterialL.S.6.762.2715.35
9999SundriesMaterialL.S.8.062.2718.30
TOTAL
3,958.24
Add 1 % Water charges on “W”
39.58
TOTAL
3,997.82
Add GST on “X” (multiplying factor 0.2127)
850.34
TOTAL
4,848.16
Add 15% CPOH on “Y”
727.22
TOTAL
5,575.38
Add Cess @ 1% on “Z”
55.75
Cost of 10 sqm
5,631.13
Cost of 1 sqm
563.11
Say
563.10

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1859. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works