CPWD Analysis of Rates · Water Proofing
Providing and mixing integral crystalline admixture for water proofing treatment to RCC structures like basement raft, retaining walls, reservior, sewage & water treatment plant, tunnels / subway and bridge deck etc. at the time of transporting of concrete into the drum of the ready-mix truck , using integral crystalline admixture @0.80% (minimum) to the weight of cement content per cubic meter of concrete) or higher as recommended by the manufacturer’s specification in reinforced cement concrete at site of work. The material shall meet the requirements as specified in ACI-212-3R-2010 i.e. by reducing permeability of concrete by more than 90%, compared with control concrete as per DIN 1048 and resistant to 16 bar hydrostatic pressure. The crystalline admixture shall be capable of self-healing of cracks up to a width of 0.50mm. The work shall be carried out all complete as per specification and the direction of the Engineer-in-charge. The product performance shall carry guarantee for 10 years against any leakage
- Item number
- 22.22
- Analysis basis
- Details of cost for 1 kg
- Priced inputs
- 4
- Derived rate
- ₹388.00 / kg
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 22.22 — Providing and mixing integral crystalline admixture for water proofing treatment to RCC structures like basement raft, retaining walls, reservior, sewage & water treatment plant, tunnels / subway and bridge deck etc. at the time of transporting of concrete into the drum of the ready-mix truck , using integral crystalline admixture @0.80% (minimum) to the weight of cement content per cubic meter of concrete) or higher as recommended by the manufacturer’s specification in reinforced cement concrete at site of work. The material shall meet the requirements as specified in ACI-212-3R-2010 i.e. by reducing permeability of concrete by more than 90%, compared with control concrete as per DIN 1048 and resistant to 16 bar hydrostatic pressure. The crystalline admixture shall be capable of self-healing of cracks up to a width of 0.50mm. The work shall be carried out all complete as per specification and the direction of the Engineer-in-charge. The product performance shall carry guarantee for 10 years against any leakage — is derived from 4 priced inputs for 1 kg and works out to ₹388.00 per kg after water charges, GST, CPOH and cess. The full build-up is below.
- MATERIAL :
- LABOUR :
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0352 | Integral crystalline admixtureMaterial | kg | 1 | 253.00 | 253.00 |
| 9999 | For measuring, making and mixing etc..Material | L.S. | 5.8 | 2.27 | 13.17 |
| 9999 | SundriesMaterial | L.S. | 1.15 | 2.27 | 2.61 |
| 9999 | Carriage of material and tools cost etc..Material | L.S. | 1.75 | 2.27 | 3.97 |
- TOTAL
- 272.75
- Add 1 % Water charges on “W”
- 2.73
- TOTAL
- 275.48
- Add GST on “X” (multiplying factor 0.2127)
- 58.59
- TOTAL
- 334.07
- Add 15% CPOH on “Y”
- 50.11
- TOTAL
- 384.18
- Add Cess @ 1% on “Z”
- 3.84
- Cost for 1.00 Kg
- 388.02
- Say
- 388.00
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1858. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.