Skip to main content
R/DAR 2023

Grading roof for water proofing treatment with

Cement mortar 1:4 (1cement : 4 coarse sand)
Item number
22.14.3
Analysis basis
one cum
Priced inputs
6
Derived rate
₹15,155.60/ ONE CUM
D-01/RATE ANALYSISITEM 22.14.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 22.14.3 (Grading roof for water proofing treatment with Cement mortar 1:4 (1cement : 4 coarse sand)) is derived from 6 priced inputs for one cum and works out to ₹15,155.60 per one cum after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Cement mortar 1:4
ANALYSIS OF RATES · ITEM 22.14.3DETAILS OF COST FOR ONE CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per Item Number 3.9 of SH: MortarsRate as per item 3.9cum14,211.704,211.70
0155LABMason (average)day1857.00857.00
0114LABBeldarday2736.001,472.00
0101LABBhistiday0.5816.00408.00
0115LABCoolieday5736.003,680.00
9999MATSundriesL.S.10.792.2724.49
BUILD-UP TO RATE
TOTAL
10,653.19
Add 1 % Water charges on “W”
+106.53
TOTAL
10,759.72
Add GST on “X” (multiplying factor 0.2127)
+2,288.59
TOTAL
13,048.31
Add 15% CPOH on “Y”
+1,957.25
TOTAL
15,005.56
Add Cess @ 1% on “Z”
+150.06
Cost of one cum
15,155.62
SAY
₹15,155.60
D-02/SOURCEPRINTED PAGE 1858
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1858

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1858. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWATER PROOFING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.