Skip to main content
R/DAR 2023

Grading roof for water proofing treatment with

Cement mortar 1:3 (1 cement : 3 coarse sand)
Item number
22.14.2
Analysis basis
one cum
Priced inputs
6
Derived rate
₹16,112.10/ ONE CUM
D-01/RATE ANALYSISITEM 22.14.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 22.14.2 (Grading roof for water proofing treatment with Cement mortar 1:3 (1 cement : 3 coarse sand)) is derived from 6 priced inputs for one cum and works out to ₹16,112.10 per one cum after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Cement mortar 1:3
ANALYSIS OF RATES · ITEM 22.14.2DETAILS OF COST FOR ONE CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per Item No.3.8 of SH:MortarsRate as per item 3.8cum14,881.954,881.95
0155LABMason (average)day1857.00857.00
0114LABBeldarday2736.001,472.00
0101LABBhistiday0.5816.00408.00
0115LABCoolieday5736.003,680.00
9999MATSundriesL.S.11.72.2726.56
BUILD-UP TO RATE
TOTAL
11,325.51
Add 1 % Water charges on “W”
+113.26
TOTAL
11,438.77
Add GST on “X” (multiplying factor 0.2127)
+2,433.03
TOTAL
13,871.80
Add 15% CPOH on “Y”
+2,080.77
TOTAL
15,952.57
Add Cess @ 1% on “Z”
+159.53
Cost of one cum
16,112.10
SAY
₹16,112.10
D-02/SOURCEPRINTED PAGE 1857
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1857

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1857. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWATER PROOFING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.