CPWD Analysis of Rates · Water Proofing

Grading roof for water proofing treatment with

Cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20mm nominal size)

Item number
22.14.1
Analysis basis
Details of cost for one cum.
Priced inputs
11
Derived rate
8,042.30 / one cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 22.14.1 Grading roof for water proofing treatment with Cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20mm nominal size) — is derived from 11 priced inputs for one cum and works out to ₹8,042.30 per one cum after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
0295Stone Aggregate (Single size) : 20 mm nominal sizeMaterialcum0.671,425.00954.75
0297Stone Aggregate (Single size) : 10 mm nominal sizeMaterialcum0.221,400.00308.00
0982Coarse sand (zone III)Materialcum0.451,450.00652.50
0367Portland Cement (OPC-43 grade)Materialtonne0.325,156.001,649.92
0114BeldarLabourday1.63736.001,199.68
0101BhistiLabourday0.7816.00571.20
0123Mason 1st classMason 1st classLabourday0.1897.0089.70
9999Sundries, brushes etc.MaterialL.S.14.32.2732.46
0002Hire charges of Concrete Mixer 0.25 to 0.40 cum with hooperHire charges of Concrete Mixer 0.25 to 0.40 cum with HopperMachineryday0.07900.0063.00
0012Vibrator (Needle type 40 mm)Machineryday0.07400.0028.00
9999Sundries for laying in terraceMaterialL.S.45.762.27103.88
TOTAL
5,653.09
Add 1 % Water charges on “W”
56.53
TOTAL
5,709.62
Add GST on “X” (multiplying factor 0.2127)
1,214.44
TOTAL
6,924.06
Add 15% CPOH on “Y”
1,038.61
TOTAL
7,962.67
Add Cess @ 1% on “Z”
79.63
Cost of one cum
8,042.30
Say
8,042.30

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1857. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.