Grading roof for water proofing treatment with
- Item number
- 22.14.1
- Analysis basis
- one cum
- Priced inputs
- 11
- Derived rate
- ₹8,042.30/ ONE CUM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 22.14.1 (Grading roof for water proofing treatment with Cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20mm nominal size)) is derived from 11 priced inputs for one cum and works out to ₹8,042.30 per one cum after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0295 | MAT | Stone Aggregate (Single size) : 20 mm nominal size | cum | 0.67 | 1,425.00 | 954.75 |
| 0297 | MAT | Stone Aggregate (Single size) : 10 mm nominal size | cum | 0.22 | 1,400.00 | 308.00 |
| 0982 | MAT | Coarse sand (zone III) | cum | 0.45 | 1,450.00 | 652.50 |
| 0367 | MAT | Portland Cement (OPC-43 grade) | tonne | 0.32 | 5,156.00 | 1,649.92 |
| 0114 | LAB | Beldar | day | 1.63 | 736.00 | 1,199.68 |
| 0101 | LAB | Bhisti | day | 0.7 | 816.00 | 571.20 |
| 0123 | LAB | Mason 1st classMason 1st class | day | 0.1 | 897.00 | 89.70 |
| 9999 | MAT | Sundries, brushes etc. | L.S. | 14.3 | 2.27 | 32.46 |
| 0002 | MACH | Hire charges of Concrete Mixer 0.25 to 0.40 cum with hooperHire charges of Concrete Mixer 0.25 to 0.40 cum with Hopper | day | 0.07 | 900.00 | 63.00 |
| 0012 | MACH | Vibrator (Needle type 40 mm) | day | 0.07 | 400.00 | 28.00 |
| 9999 | MAT | Sundries for laying in terrace | L.S. | 45.76 | 2.27 | 103.88 |
- TOTAL
- 5,653.09
- Add 1 % Water charges on “W”
- +56.53
- TOTAL
- 5,709.62
- Add GST on “X” (multiplying factor 0.2127)
- +1,214.44
- TOTAL
- 6,924.06
- Add 15% CPOH on “Y”
- +1,038.61
- TOTAL
- 7,962.67
- Add Cess @ 1% on “Z”
- +79.63
- Cost of one cum
- 8,042.30
- SAY
- ₹8,042.30
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1857
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1857. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.