Grading roof for water proofing treatment with

Cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20mm nominal size)
Item number
22.14.1
Analysis basis
one cum
Priced inputs
11
Derived rate
₹8,042.30/ ONE CUM
D-01/RATE ANALYSISITEM 22.14.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 22.14.1 (Grading roof for water proofing treatment with Cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20mm nominal size)) is derived from 11 priced inputs for one cum and works out to ₹8,042.30 per one cum after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 22.14.1DETAILS OF COST FOR ONE CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0295MATStone Aggregate (Single size) : 20 mm nominal sizecum0.671,425.00954.75
0297MATStone Aggregate (Single size) : 10 mm nominal sizecum0.221,400.00308.00
0982MATCoarse sand (zone III)cum0.451,450.00652.50
0367MATPortland Cement (OPC-43 grade)tonne0.325,156.001,649.92
0114LABBeldarday1.63736.001,199.68
0101LABBhistiday0.7816.00571.20
0123LABMason 1st classMason 1st classday0.1897.0089.70
9999MATSundries, brushes etc.L.S.14.32.2732.46
0002MACHHire charges of Concrete Mixer 0.25 to 0.40 cum with hooperHire charges of Concrete Mixer 0.25 to 0.40 cum with Hopperday0.07900.0063.00
0012MACHVibrator (Needle type 40 mm)day0.07400.0028.00
9999MATSundries for laying in terraceL.S.45.762.27103.88
BUILD-UP TO RATE
TOTAL
5,653.09
Add 1 % Water charges on “W”
+56.53
TOTAL
5,709.62
Add GST on “X” (multiplying factor 0.2127)
+1,214.44
TOTAL
6,924.06
Add 15% CPOH on “Y”
+1,038.61
TOTAL
7,962.67
Add Cess @ 1% on “Z”
+79.63
Cost of one cum
8,042.30
SAY
₹8,042.30
D-02/SOURCEPRINTED PAGE 1857
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1857

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1857. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWATER PROOFING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.