Deduct for omitting in water proofing treatment final course of spreading stone grit 6 mm down size or pea sized gravel

at 8 cudm per sqm
Item number
22.13.2
Analysis basis
10 sqm
Priced inputs
3
Derived rate
₹22.10/ SQM
D-01/RATE ANALYSISITEM 22.13.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 22.13.2 (Deduct for omitting in water proofing treatment final course of spreading stone grit 6 mm down size or pea sized gravel : at 8 cudm per sqm) is derived from 3 priced inputs for 10 sqm and works out to ₹22.10 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 8x10 = 80 cudm
ANALYSIS OF RATES · ITEM 22.13.2DETAILS OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1177MATStone grit 8 mm and down size or pea sized gravelStone grit 6 mm and down size or pea sized gravelcum0.08985.0078.80
9999MATLabour for screening and spreading gritL.S.26.912.2761.09
9999MATSundriesL.S.6.762.2715.35
BUILD-UP TO RATE
TOTAL
155.24
Add 1 % Water charges on “W”
+1.55
TOTAL
156.79
Add GST on “X” (multiplying factor 0.2127)
+33.35
TOTAL
190.14
Add 15% CPOH on “Y”
+28.52
TOTAL
218.66
Add Cess @ 1% on “Z”
+2.19
Cost of 10.00 Sqm.
220.85
Cost of 1.00 Sqm.
22.09
SAY
₹22.10
D-02/SOURCEPRINTED PAGE 1856
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1856

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1856. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.