CPWD Analysis of Rates · Water Proofing

Deduct for omitting in water proofing treatment final course of spreading stone grit 6 mm down size or pea sized gravel

at 6 cudm per sqm

Item number
22.13.1
Analysis basis
Details of cost for 10 sqm.
Priced inputs
3
Derived rate
17.55 / Sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 22.13.1 Deduct for omitting in water proofing treatment final course of spreading stone grit 6 mm down size or pea sized gravel : at 6 cudm per sqm — is derived from 3 priced inputs for 10 sqm and works out to ₹17.55 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • 6x10 = 60 cudm
CodeInputUnitQuantityRate (INR)Amount (INR)
1177Stone grit 6 mm and down size or pea sized gravelMaterialcum0.06985.0059.10
9999Labour for screening and spreading gritMaterialL.S.21.582.2748.99
9999SundriesMaterialL.S.6.762.2715.35
TOTAL
123.44
Add 1 % Water charges on “W”
1.23
TOTAL
124.67
Add GST on “X” (multiplying factor 0.2127)
26.52
TOTAL
151.19
Add 15% CPOH on “Y”
22.68
TOTAL
173.87
Add Cess @ 1% on “Z”
1.74
Cost of 10.00 Sqm.
175.61
Cost of 1.00 Sqm.
17.56
Say
17.55

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1856. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works