Skip to main content
R/DAR 2023

Supplying and applying bituminous solution primer on roof and / or wall surface at 0.24 litre per sqm

Item number
22.12
Analysis basis
10 sq
Priced inputs
5
Derived rate
₹59.45/ SQM
D-01/RATE ANALYSISITEM 22.12

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 22.12 (Supplying and applying bituminous solution primer on roof and / or wall surface at 0.24 litre per sqm) is derived from 5 priced inputs for 10 sq and works out to ₹59.45 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 22.12DETAILS OF COST FOR 10 SQ. METRES
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0316MATBitumen solution primer of approved qualitylitre2.450.00120.00
9977MATCARRIAGEL.S.1.432.273.25
0131LABPainterday0.17816.00138.72
0114LABBeldarday0.17736.00125.12
9999MATSundries brushes etc.L.S.13.522.2730.69
BUILD-UP TO RATE
TOTAL
417.78
Add 1 % Water charges on “W”
+4.18
TOTAL
421.96
Add GST on “X” (multiplying factor 0.2127)
+89.75
TOTAL
511.71
Add 15% CPOH on “Y”
+76.76
TOTAL
588.47
Add Cess @ 1% on “Z”
+5.88
Cost of 10.00 Sqm.
594.35
Cost of 1.00 Sqm.
59.44
SAY
₹59.45
D-02/SOURCEPRINTED PAGE 1855
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1855

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1855. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWATER PROOFING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.