CPWD Analysis of Rates · Water Proofing

Supplying and applying bituminous solution primer on roof and / or wall surface at 0.24 litre per sqm

Item number
22.12
Analysis basis
Details of cost for 10 sq. metres
Priced inputs
5
Derived rate
59.45 / Sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 22.12 Supplying and applying bituminous solution primer on roof and / or wall surface at 0.24 litre per sqm — is derived from 5 priced inputs for 10 sq and works out to ₹59.45 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
0316Bitumen solution primer of approved qualityMateriallitre2.450.00120.00
9977CARRIAGEMaterialL.S.1.432.273.25
0131PainterLabourday0.17816.00138.72
0114BeldarLabourday0.17736.00125.12
9999Sundries brushes etc.MaterialL.S.13.522.2730.69
TOTAL
417.78
Add 1 % Water charges on “W”
4.18
TOTAL
421.96
Add GST on “X” (multiplying factor 0.2127)
89.75
TOTAL
511.71
Add 15% CPOH on “Y”
76.76
TOTAL
588.47
Add Cess @ 1% on “Z”
5.88
Cost of 10.00 Sqm.
594.35
Cost of 1.00 Sqm.
59.44
Say
59.45

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1855. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.