Skip to main content

CPWD Analysis of Rates · Structural Glazing Aluminium Composite Panel

Extra for openable side / top hung vision glass panels (IGUs) including providing and supplying at site all accessories and hardwares for the openable panels as specified and of the approved make such as heavy duty stainless steel friction hinges, min 4 -point cremone locking sets with stainless steel plates, handles, buffers etc. including necessary stainless steel screws/ fasteners, nuts, bolts, washers etc. all complete as per the Architectural drawings, as per the approved shop drawings, as specified and as directed by the Engineerin-Charge

Item number
25.4
Analysis basis
Details of cost for 1.76 sqm
Priced inputs
12
Derived rate
3,671.50 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 25.4 Extra for openable side / top hung vision glass panels (IGUs) including providing and supplying at site all accessories and hardwares for the openable panels as specified and of the approved make such as heavy duty stainless steel friction hinges, min 4 -point cremone locking sets with stainless steel plates, handles, buffers etc. including necessary stainless steel screws/ fasteners, nuts, bolts, washers etc. all complete as per the Architectural drawings, as per the approved shop drawings, as specified and as directed by the Engineerin-Charge — is derived from 12 priced inputs for 1.76 sqm and works out to ₹3,671.50 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • Width of the unit 1.6 m
  • Shuttter Weight
  • Height of the unit 1.1 m
  • Outer glass 6 mm
  • Area 1.76 sqm
  • Inner glass 6 mm
  • Aluminium Weight per sqm 7.78 Kg
  • Al weight = 1.76x7.78 = 13.7 Kg
  • No of Locking Point 4 no Total 67 Kg
  • Wedge Block 1 no
CodeInputUnitQuantityRate (INR)Amount (INR)
2619Extra for 6 mm thick clear heat strengthened glassMaterialeach3134.00402.00
2611EPDM Gasket in Kg (Above 60 g / m)Materialkg0.8163.00130.40
2614SS Screws of sizes for structural glazing / ACP CladdingMaterialeach495.00245.00
2615Protective TapeMaterialmetre1.7623.0040.48
2620ARMS GS HD -TOP HUNG -20”-TYPE P-COUPLEARMS GS HD - Top Hung -20”- Type P- CoupleMaterialpair11,416.001,416.00
2621Connection BlockConnection Block for vision glass panelMaterialeach237.0074.00
2622Curtain wall strikerCurtain wall striker for vision glass panelMaterialeach489.00356.00
2623Adjustable Fastening PawlAdjustable Fastening Rawl for vision glass panelMaterialeach437.00148.00
2624Corner driveCorner drive for vision glass panelMaterialeach2267.00534.00
2625Top wedge BlockTop wedge Block for vision glass panelMaterialeach1124.00124.00
9999SundriesMaterialL.S.1182.27267.86
9999Sundries (For Fabrication)MaterialL.S.354.362.27804.40
TOTAL
4,542.14
Add 1 % Water charges on “W”
45.42
TOTAL
4,587.56
Add GST on “X” (multiplying factor 0.2127)
975.77
TOTAL
5,563.33
Add 15% CPOH on “Y”
834.50
TOTAL
6,397.83
Add Cess @ 1% on “Z”
63.98
Cost for 1.76 sqm
6,461.81
Cost for 1 sqm
3,671.48
Say
3,671.50

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1900. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works