CPWD Analysis of Rates · Stone Work
Coursed rubble masonry with hard stone (first or second sort) in superstructure above plinth level and upto floor five level
Masonry work (second sort), in cement mortar 1:6 (1 cement: 6 coarse sand)
- Item number
- 7.8.2
- Analysis basis
- Details of cost for 1 cum
- Priced inputs
- 9
- Derived rate
- ₹10,128.10 / cum
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 7.8.2 — Coursed rubble masonry with hard stone (first or second sort) in superstructure above plinth level and upto floor five level Masonry work (second sort), in cement mortar 1:6 (1 cement: 6 coarse sand) — is derived from 9 priced inputs for 1 cum and works out to ₹10,128.10 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- Cement mortar 1 : 6 (1 cement : 6 coarse
- sand)
- Extra labour for lifting of material (above
- floor two level up to floor five level)
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| Rate as per Item Number 3.11 of SH: MortarsRate as per item 3.11Sub-analysis | cum | 0.3 | 3,541.40 | 1,062.42 | |
| 1157 | Stone for masonry workMaterial | cum | 1.1 | 1,250.00 | 1,375.00 |
| 1154 | Through and bond stone size 24 x24 x39 cmThrough and bond stoneMaterial | 100 Nos | 0.07 | 5,000.00 | 350.00 |
| 0125 | Mason (for plain stone work) 2nd class)Mason (for plain stone work) 2nd classLabour | day | 2.02 | 816.00 | 1,648.32 |
| 0114 | BeldarLabour | day | 1.59 | 736.00 | 1,170.24 |
| 0115 | CoolieLabour | day | 0.71 | 736.00 | 522.56 |
| 0101 | BhistiLabour | day | 0.09 | 816.00 | 73.44 |
| 0115 | CoolieLabour | day | 1.13 | 736.00 | 831.68 |
| 9999 | Sundries, scaffolding etc.Material | L.S. | 37.7 | 2.27 | 85.58 |
- TOTAL
- 7,119.24
- Add 1 % Water charges on “W”
- 71.19
- TOTAL
- 7,190.43
- Add GST on “X” (multiplying factor 0.2127)
- 1,529.40
- TOTAL
- 8,719.83
- Add 15% CPOH on “Y”
- 1,307.97
- TOTAL
- 10,027.80
- Add Cess @ 1% on “Z”
- 100.28
- Cost of 1 cum.
- 10,128.08
- Say
- 10,128.10
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 349. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.