CPWD Analysis of Rates · Stone Work

Coursed rubble masonry with hard stone (first or second sort) in superstructure above plinth level and upto floor five level

Masonry work (first sort), in cement mortar 1:6 (1 cement : 6 coarse sand)

Item number
7.8.1
Analysis basis
Details of cost for 1 cum
Priced inputs
9
Derived rate
10,741.60 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 7.8.1 Coursed rubble masonry with hard stone (first or second sort) in superstructure above plinth level and upto floor five level Masonry work (first sort), in cement mortar 1:6 (1 cement : 6 coarse sand) — is derived from 9 priced inputs for 1 cum and works out to ₹10,741.60 per cum after water charges, GST, CPOH and cess. The full build-up is below.

  • Cement mortar 1 : 6 (1 cement : 6 coarse
  • sand)
  • Extra labour for lifting of material (above
  • floor two level up to floor five level)
CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per Item Number 3.11 of SH: MortarsRate as per item 3.11Sub-analysiscum0.33,541.401,062.42
1157Stone for masonry workMaterialcum1.211,250.001,512.50
1154Through and bond stone size 24 x 24 x39 cmThrough and bond stoneMaterial100 Nos0.075,000.00350.00
0125Mason (for plain stone work) 2nd class)Mason (for plain stone work) 2nd classLabourday2.38816.001,942.08
0114BeldarLabourday1.59736.001,170.24
0115CoolieLabourday0.71736.00522.56
0101BhistiLabourday0.09816.0073.44
0115CoolieLabourday1.13736.00831.68
9999Sundries, scaffolding etc.MaterialL.S.37.72.2785.58
TOTAL
7,550.50
Add 1 % Water charges on “W”
75.51
TOTAL
7,626.01
Add GST on “X” (multiplying factor 0.2127)
1,622.05
TOTAL
9,248.06
Add 15% CPOH on “Y”
1,387.21
TOTAL
10,635.27
Add Cess @ 1% on “Z”
106.35
Cost of 1 cum.
10,741.62
Say
10,741.60

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 348. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works