Extra for coursed rubble masonry with hard stone (first or second sort) in
- Item number
- 7.10.1
- Analysis basis
- 1 cum
- Priced inputs
- 2
- Derived rate
- ₹1,060.50/ CUM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 7.10.1 (Extra for coursed rubble masonry with hard stone (first or second sort) in: Square or rectangular pillars) is derived from 2 priced inputs for 1 cum and works out to ₹1,060.50 per cum after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0125 | LAB | Mason (for plain stone work) 2nd class)Mason (for plain stone work) 2nd class | day | 0.67 | 816.00 | 546.72 |
| 0115 | LAB | Coolie | day | 0.27 | 736.00 | 198.72 |
- TOTAL
- 745.44
- Add 1 % Water charges on “W”
- +7.45
- TOTAL
- 752.89
- Add GST on “X” (multiplying factor 0.2127)
- +160.14
- TOTAL
- 913.03
- Add 15% CPOH on “Y”
- +136.95
- TOTAL
- 1,049.98
- Add Cess @ 1% on “Z”
- +10.50
- Cost of 1 cum.
- 1,060.48
- SAY
- ₹1,060.50
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 349
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 349. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.