Extra for coursed rubble masonry with hard stone (first or second sort) in

Circular pillars
Item number
7.10.2
Analysis basis
1 cum
Priced inputs
3
Derived rate
₹2,874.20/ CUM
D-01/RATE ANALYSISITEM 7.10.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 7.10.2 (Extra for coursed rubble masonry with hard stone (first or second sort) in: Circular pillars) is derived from 3 priced inputs for 1 cum and works out to ₹2,874.20 per cum after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Labour for cutting and dressing stones-
ANALYSIS OF RATES · ITEM 7.10.2DETAILS OF COST FOR 1 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1157MATStone for masonry workcum0.321,250.00400.00
0125LABMason (for plain stone work) 2nd class)Mason (for plain stone work) 2nd classday1.67816.001,362.72
0115LABCoolieday0.35736.00257.60
BUILD-UP TO RATE
TOTAL
2,020.32
Add 1 % Water charges on “W”
+20.20
TOTAL
2,040.52
Add GST on “X” (multiplying factor 0.2127)
+434.02
TOTAL
2,474.54
Add 15% CPOH on “Y”
+371.18
TOTAL
2,845.72
Add Cess @ 1% on “Z”
+28.46
Cost of 1 cum
2,874.18
SAY
₹2,874.20
D-02/SOURCEPRINTED PAGE 350
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
350

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 350. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSSTONE WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.