CPWD Analysis of Rates · Stone Work
Extra for coursed rubble masonry with hard stone (first or second sort) curved on plan for a mean radius not exceeding 6 m
- Item number
- 7.11
- Analysis basis
- Details of cost for 1 cum
- Priced inputs
- 3
- Derived rate
- ₹1,133.65 / cum
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 7.11 — Extra for coursed rubble masonry with hard stone (first or second sort) curved on plan for a mean radius not exceeding 6 m — is derived from 3 priced inputs for 1 cum and works out to ₹1,133.65 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- Extra
- Labour for cutting and dressing stones-
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 1157 | Stone for masonry workMaterial | cum | 0.11 | 1,250.00 | 137.50 |
| 0125 | Mason (for plain stone work) 2nd class)Mason (for plain stone work) 2nd classLabour | day | 0.33 | 816.00 | 269.28 |
| 0115 | CoolieLabour | day | 0.53 | 736.00 | 390.08 |
- TOTAL
- 796.86
- Add 1 % Water charges on “W”
- 7.97
- TOTAL
- 804.83
- Add GST on “X” (multiplying factor 0.2127)
- 171.19
- TOTAL
- 976.02
- Add 15% CPOH on “Y”
- 146.40
- TOTAL
- 1,122.42
- Add Cess @ 1% on “Z”
- 11.22
- Cost of 1 cum.
- 1,133.64
- Say
- 1,133.65
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 350. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.