CPWD Analysis of Rates · Stone Work

Extra for coursed rubble masonry with hard stone (first or second sort) curved on plan for a mean radius not exceeding 6 m

Item number
7.11
Analysis basis
Details of cost for 1 cum
Priced inputs
3
Derived rate
1,133.65 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 7.11 Extra for coursed rubble masonry with hard stone (first or second sort) curved on plan for a mean radius not exceeding 6 m — is derived from 3 priced inputs for 1 cum and works out to ₹1,133.65 per cum after water charges, GST, CPOH and cess. The full build-up is below.

  • Extra
  • Labour for cutting and dressing stones-
CodeInputUnitQuantityRate (INR)Amount (INR)
1157Stone for masonry workMaterialcum0.111,250.00137.50
0125Mason (for plain stone work) 2nd class)Mason (for plain stone work) 2nd classLabourday0.33816.00269.28
0115CoolieLabourday0.53736.00390.08
TOTAL
796.86
Add 1 % Water charges on “W”
7.97
TOTAL
804.83
Add GST on “X” (multiplying factor 0.2127)
171.19
TOTAL
976.02
Add 15% CPOH on “Y”
146.40
TOTAL
1,122.42
Add Cess @ 1% on “Z”
11.22
Cost of 1 cum.
1,133.64
Say
1,133.65

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 350. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.