Stone work in plain ashlar in super structure upto floor five level in cement mortar 1:6 (1 cement : 6 coarse sand) including pointing with cement mortar 1:2 (1 white cement : 2 stone dust) with an admixture of pigment matching the stone shade : One face dressed
- Item number
- 7.12.1.1
- Analysis basis
- 10 cudm
- Priced inputs
- 15
- Derived rate
- ₹68,294.00/ CUM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 7.12.1.1 (Stone work in plain ashlar in super structure upto floor five level in cement mortar 1:6 (1 cement : 6 coarse sand) including pointing with cement mortar 1:2 (1 white cement : 2 stone dust) with an admixture of pigment matching the stone shade : One face dressed Red sand stone) is derived from 15 priced inputs for 10 cudm and works out to ₹68,294.00 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- Red sand stone
- Finished work = 10 cudm.+ Add wastage
- @ 33.3% = 3.33 cudm. Total = 13.33
- cudm
- Extra labour for lifting of materials upto
- floor V level (0.01x1.50 = 0.015)
- Dressing charges
- Fixing charges
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 1160 | MAT | Red sand stone block | 10 cudm | 1.333 | 130.00 | 173.29 |
| 0115 | LAB | Coolie | day | 0.015 | 736.00 | 11.04 |
| 0125 | LAB | Mason (for plain stone work) 2nd class)Mason (for plain stone work) 2nd class | day | 0.088 | 816.00 | 71.81 |
| 0102 | LAB | Blacksmith 1st class | day | 0.006 | 897.00 | 5.38 |
| 0114 | LAB | Beldar | day | 0.044 | 736.00 | 32.38 |
| 0115 | LAB | Coolie | day | 0.022 | 736.00 | 16.19 |
| 0100 | LAB | Bandhani | day | 0.044 | 816.00 | 35.90 |
| 0125 | LAB | Mason (for plain stone work) 2nd class)Mason (for plain stone work) 2nd class | day | 0.044 | 816.00 | 35.90 |
| 0102 | LAB | Blacksmith 1st class | day | 0.006 | 897.00 | 5.38 |
| 0114 | LAB | Beldar | day | 0.022 | 736.00 | 16.19 |
| 0115 | LAB | Coolie | day | 0.022 | 736.00 | 16.19 |
| 0100 | LAB | Bandhani | day | 0.022 | 816.00 | 17.95 |
| 0101 | LAB | Bhisti | day | 0.022 | 816.00 | 17.95 |
| 9999 | MAT | Scafolding | L.S. | 2.73 | 2.27 | 6.20 |
| 9999 | MAT | Mortar for laying and pointing | L.S. | 8.06 | 2.27 | 18.30 |
- TOTAL
- 480.05
- Add 1 % Water charges on “W”
- +4.80
- TOTAL
- 484.85
- Add GST on “X” (multiplying factor 0.2127)
- +103.13
- TOTAL
- 587.98
- Add 15% CPOH on “Y”
- +88.20
- TOTAL
- 676.18
- Add Cess @ 1% on “Z”
- +6.76
- Cost of 10 cudm.
- 682.94
- Cost of 1 cum.
- 68,294.00
- SAY
- ₹68,294.00
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 351
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 351. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.