Stone work in plain ashlar in super structure upto floor five level in cement mortar 1:6 (1 cement : 6 coarse sand) including pointing with cement mortar 1:2 (1 white cement : 2 stone dust) with an admixture of pigment matching the stone shade : One face dressed

Red sand stone
Item number
7.12.1.1
Analysis basis
10 cudm
Priced inputs
15
Derived rate
₹68,294.00/ CUM
D-01/RATE ANALYSISITEM 7.12.1.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 7.12.1.1 (Stone work in plain ashlar in super structure upto floor five level in cement mortar 1:6 (1 cement : 6 coarse sand) including pointing with cement mortar 1:2 (1 white cement : 2 stone dust) with an admixture of pigment matching the stone shade : One face dressed Red sand stone) is derived from 15 priced inputs for 10 cudm and works out to ₹68,294.00 per cum after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Red sand stone
  • Finished work = 10 cudm.+ Add wastage
  • @ 33.3% = 3.33 cudm. Total = 13.33
  • cudm
  • Extra labour for lifting of materials upto
  • floor V level (0.01x1.50 = 0.015)
  • Dressing charges
  • Fixing charges
ANALYSIS OF RATES · ITEM 7.12.1.1DETAILS OF COST FOR 10 CUDM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1160MATRed sand stone block10 cudm1.333130.00173.29
0115LABCoolieday0.015736.0011.04
0125LABMason (for plain stone work) 2nd class)Mason (for plain stone work) 2nd classday0.088816.0071.81
0102LABBlacksmith 1st classday0.006897.005.38
0114LABBeldarday0.044736.0032.38
0115LABCoolieday0.022736.0016.19
0100LABBandhaniday0.044816.0035.90
0125LABMason (for plain stone work) 2nd class)Mason (for plain stone work) 2nd classday0.044816.0035.90
0102LABBlacksmith 1st classday0.006897.005.38
0114LABBeldarday0.022736.0016.19
0115LABCoolieday0.022736.0016.19
0100LABBandhaniday0.022816.0017.95
0101LABBhistiday0.022816.0017.95
9999MATScafoldingL.S.2.732.276.20
9999MATMortar for laying and pointingL.S.8.062.2718.30
BUILD-UP TO RATE
TOTAL
480.05
Add 1 % Water charges on “W”
+4.80
TOTAL
484.85
Add GST on “X” (multiplying factor 0.2127)
+103.13
TOTAL
587.98
Add 15% CPOH on “Y”
+88.20
TOTAL
676.18
Add Cess @ 1% on “Z”
+6.76
Cost of 10 cudm.
682.94
Cost of 1 cum.
68,294.00
SAY
₹68,294.00
D-02/SOURCEPRINTED PAGE 351
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
351

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 351. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSSTONE WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.