Coursed rubble masonry (first sort) with hard stone in foundation and plinth with
- Item number
- 7.6.1
- Analysis basis
- 1 cum
- Priced inputs
- 8
- Derived rate
- ₹8,812.05/ CUM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 7.6.1 (Coursed rubble masonry (first sort) with hard stone in foundation and plinth with : Cement mortar 1:6 (1 cement : 6 coarse sand)) is derived from 8 priced inputs for 1 cum and works out to ₹8,812.05 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- Cement mortar 1 : 6 (1 cement : 6 coarse
- sand)
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| SUB | Rate as per Item Number 3.11 of SH: MortarsRate as per item 3.11 | cum | 0.3 | 3,541.40 | 1,062.42 | |
| 1157 | MAT | Stone for masonry work | cum | 1.21 | 1,250.00 | 1,512.50 |
| 1154 | MAT | Through and bond stone size 24 x24 x39 cmThrough and bond stone | 100 Nos | 0.07 | 5,000.00 | 350.00 |
| 0125 | LAB | Mason (for plain stone work) 2nd class)Mason (for plain stone work) 2nd class | day | 2.12 | 816.00 | 1,729.92 |
| 0114 | LAB | Beldar | day | 1.24 | 736.00 | 912.64 |
| 0115 | LAB | Coolie | day | 0.71 | 736.00 | 522.56 |
| 0101 | LAB | Bhisti | day | 0.09 | 816.00 | 73.44 |
| 9999 | MAT | Sundries | L.S. | 13.52 | 2.27 | 30.69 |
- TOTAL
- 6,194.17
- Add 1 % Water charges on “W”
- +61.94
- TOTAL
- 6,256.11
- Add GST on “X” (multiplying factor 0.2127)
- +1,330.67
- TOTAL
- 7,586.78
- Add 15% CPOH on “Y”
- +1,138.02
- TOTAL
- 8,724.80
- Add Cess @ 1% on “Z”
- +87.25
- Cost of 1 cum.
- 8,812.05
- SAY
- ₹8,812.05
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 347
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 347. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.