Extra for random rubble masonry with hard stone curved on plan for a mean radius not exceeding 6 m

Item number
7.5
Analysis basis
1 cum
Priced inputs
3
Derived rate
₹1,046.20/ CUM
D-01/RATE ANALYSISITEM 7.5

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 7.5 (Extra for random rubble masonry with hard stone curved on plan for a mean radius not exceeding 6 m) is derived from 3 priced inputs for 1 cum and works out to ₹1,046.20 per cum after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Labour for cutting and dressing stones-
ANALYSIS OF RATES · ITEM 7.5DETAILS OF COST FOR 1 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1157MATStone for masonry workcum0.11,250.00125.00
0125LABMason (for plain stone work) 2nd class)Mason (for plain stone work) 2nd classday0.27816.00220.32
0115LABCoolieday0.53736.00390.08
BUILD-UP TO RATE
TOTAL
735.40
Add 1 % Water charges on “W”
+7.35
TOTAL
742.75
Add GST on “X” (multiplying factor 0.2127)
+157.98
TOTAL
900.73
Add 15% CPOH on “Y”
+135.11
TOTAL
1,035.84
Add Cess @ 1% on “Z”
+10.36
Cost of 1 cum.
1,046.20
SAY
₹1,046.20
D-02/SOURCEPRINTED PAGE 347
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
347

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 347. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSSTONE WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.