CPWD Analysis of Rates · Stone Work

Extra for random rubble masonry with hard stone in

Circular pillars

Item number
7.4.2
Analysis basis
Details of cost for 1 cum
Priced inputs
3
Derived rate
2,530.60 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 7.4.2 Extra for random rubble masonry with hard stone in : Circular pillars — is derived from 3 priced inputs for 1 cum and works out to ₹2,530.60 per cum after water charges, GST, CPOH and cess. The full build-up is below.

  • Labour for cutting and dressing stones-
CodeInputUnitQuantityRate (INR)Amount (INR)
1157Stone for masonry workMaterialcum0.291,250.00362.50
0125Mason (for plain stone work) 2nd class)Mason (for plain stone work) 2nd classLabourday1.42816.001,158.72
0115CoolieLabourday0.35736.00257.60
TOTAL
1,778.82
Add 1 % Water charges on “W”
17.79
TOTAL
1,796.61
Add GST on “X” (multiplying factor 0.2127)
382.14
TOTAL
2,178.75
Add 15% CPOH on “Y”
326.81
TOTAL
2,505.56
Add Cess @ 1% on “Z”
25.06
Cost of 1 cum
2,530.62
Say
2,530.60

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 346. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works