Extra for random rubble masonry with hard stone in
- Item number
- 7.4.2
- Analysis basis
- 1 cum
- Priced inputs
- 3
- Derived rate
- ₹2,530.60/ CUM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 7.4.2 (Extra for random rubble masonry with hard stone in : Circular pillars) is derived from 3 priced inputs for 1 cum and works out to ₹2,530.60 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- Labour for cutting and dressing stones-
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 1157 | MAT | Stone for masonry work | cum | 0.29 | 1,250.00 | 362.50 |
| 0125 | LAB | Mason (for plain stone work) 2nd class)Mason (for plain stone work) 2nd class | day | 1.42 | 816.00 | 1,158.72 |
| 0115 | LAB | Coolie | day | 0.35 | 736.00 | 257.60 |
- TOTAL
- 1,778.82
- Add 1 % Water charges on “W”
- +17.79
- TOTAL
- 1,796.61
- Add GST on “X” (multiplying factor 0.2127)
- +382.14
- TOTAL
- 2,178.75
- Add 15% CPOH on “Y”
- +326.81
- TOTAL
- 2,505.56
- Add Cess @ 1% on “Z”
- +25.06
- Cost of 1 cum
- 2,530.62
- SAY
- ₹2,530.60
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 346
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 346. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.