Skip to main content
R/DAR 2023

Extra for random rubble masonry with hard stone in

Square or rectangular pillars
Item number
7.4.1
Analysis basis
1 cum
Priced inputs
2
Derived rate
₹956.00/ CUM
D-01/RATE ANALYSISITEM 7.4.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 7.4.1 (Extra for random rubble masonry with hard stone in : Square or rectangular pillars) is derived from 2 priced inputs for 1 cum and works out to ₹956.00 per cum after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 7.4.1DETAILS OF COST FOR 1 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0125LABMason (for plain stone work) 2nd class)Mason (for plain stone work) 2nd classday0.58816.00473.28
0115LABCoolieday0.27736.00198.72
BUILD-UP TO RATE
TOTAL
672.00
Add 1 % Water charges on “W”
+6.72
TOTAL
678.72
Add GST on “X” (multiplying factor 0.2127)
+144.36
TOTAL
823.08
Add 15% CPOH on “Y”
+123.46
TOTAL
946.54
Add Cess @ 1% on “Z”
+9.47
Cost of 1 cum.
956.01
SAY
₹956.00
D-02/SOURCEPRINTED PAGE 346
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
346

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 346. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSSTONE WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.