Random rubble masonry with hard stone in superstructure above plinth level and upto floor five level, including leveling up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate 20 mm nominal size) at window sills, ceiling level and the like

Cement mortar 1:6 (1 cement : 6 coarse sand)
Item number
7.2.1
Analysis basis
1 cum
Priced inputs
10
Derived rate
₹9,275.45/ CUM
D-01/RATE ANALYSISITEM 7.2.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 7.2.1 (Random rubble masonry with hard stone in superstructure above plinth level and upto floor five level, including leveling up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate 20 mm nominal size) at window sills, ceiling level and the like Cement mortar 1:6 (1 cement : 6 coarse sand)) is derived from 10 priced inputs for 1 cum and works out to ₹9,275.45 per cum after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Carriage of stoneExtra labour for lifting of material (above
  • floor two level up to floor five level)
ANALYSIS OF RATES · ITEM 7.2.1DETAILS OF COST FOR 1 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1157MATStone for masonry workcum11,250.001,250.00
1154MATThrough and bond stone size 24 x 24 x39 cmThrough and bond stone100 Nos0.075,000.00350.00
SUBRate as per Item Number 3.11 of SH: MortarsRate as per item 3.11cum0.333,541.401,168.66
0125LABMason (for plain stone work) 2nd class)Mason (for plain stone work) 2nd classday1.34816.001,093.44
0114LABBeldarday1.45736.001,067.20
0115LABCoolieday0.71736.00522.56
0101LABBhistiday0.09816.0073.44
9999MATCement concrete 1:6:12L.S.56.552.27128.37
0115LABCoolieday1.13736.00831.68
9999MATSundriesL.S.15.212.2734.53
BUILD-UP TO RATE
TOTAL
6,519.88
Add 1 % Water charges on “W”
+65.20
TOTAL
6,585.08
Add GST on “X” (multiplying factor 0.2127)
+1,400.65
TOTAL
7,985.73
Add 15% CPOH on “Y”
+1,197.86
TOTAL
9,183.59
Add Cess @ 1% on “Z”
+91.84
Cost of 1 cum.
9,275.43
SAY
₹9,275.45
D-02/SOURCEPRINTED PAGE 345
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
345

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 345. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.