Random rubble masonry with hard stone in superstructure above plinth level and upto floor five level, including leveling up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate 20 mm nominal size) at window sills, ceiling level and the like
- Item number
- 7.2.1
- Analysis basis
- 1 cum
- Priced inputs
- 10
- Derived rate
- ₹9,275.45/ CUM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 7.2.1 (Random rubble masonry with hard stone in superstructure above plinth level and upto floor five level, including leveling up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate 20 mm nominal size) at window sills, ceiling level and the like Cement mortar 1:6 (1 cement : 6 coarse sand)) is derived from 10 priced inputs for 1 cum and works out to ₹9,275.45 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- Carriage of stoneExtra labour for lifting of material (above
- floor two level up to floor five level)
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 1157 | MAT | Stone for masonry work | cum | 1 | 1,250.00 | 1,250.00 |
| 1154 | MAT | Through and bond stone size 24 x 24 x39 cmThrough and bond stone | 100 Nos | 0.07 | 5,000.00 | 350.00 |
| SUB | Rate as per Item Number 3.11 of SH: MortarsRate as per item 3.11 | cum | 0.33 | 3,541.40 | 1,168.66 | |
| 0125 | LAB | Mason (for plain stone work) 2nd class)Mason (for plain stone work) 2nd class | day | 1.34 | 816.00 | 1,093.44 |
| 0114 | LAB | Beldar | day | 1.45 | 736.00 | 1,067.20 |
| 0115 | LAB | Coolie | day | 0.71 | 736.00 | 522.56 |
| 0101 | LAB | Bhisti | day | 0.09 | 816.00 | 73.44 |
| 9999 | MAT | Cement concrete 1:6:12 | L.S. | 56.55 | 2.27 | 128.37 |
| 0115 | LAB | Coolie | day | 1.13 | 736.00 | 831.68 |
| 9999 | MAT | Sundries | L.S. | 15.21 | 2.27 | 34.53 |
- TOTAL
- 6,519.88
- Add 1 % Water charges on “W”
- +65.20
- TOTAL
- 6,585.08
- Add GST on “X” (multiplying factor 0.2127)
- +1,400.65
- TOTAL
- 7,985.73
- Add 15% CPOH on “Y”
- +1,197.86
- TOTAL
- 9,183.59
- Add Cess @ 1% on “Z”
- +91.84
- Cost of 1 cum.
- 9,275.43
- SAY
- ₹9,275.45
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 345
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 345. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.