CPWD Analysis of Rates · Stone Work
Random rubble masonry with hard stone in foundation and plinth including levelling up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate 20 mm nominal size) upto plinth level with
Cement mortar 1:6 (1 cement : 6 coarse sand)
- Item number
- 7.1.1
- Analysis basis
- Details of cost for 1 cum
- Priced inputs
- 9
- Derived rate
- ₹7,311.25 / cum
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 7.1.1 — Random rubble masonry with hard stone in foundation and plinth including levelling up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate 20 mm nominal size) upto plinth level with : Cement mortar 1:6 (1 cement : 6 coarse sand) — is derived from 9 priced inputs for 1 cum and works out to ₹7,311.25 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- Carriage:
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 1157 | Stone for masonry workMaterial | cum | 1 | 1,250.00 | 1,250.00 |
| 1154 | Through and bond stone size 24 x24 x39 cmThrough and bond stoneMaterial | 100 Nos | 0.07 | 5,000.00 | 350.00 |
| Rate as per Item Number 3.11 of SH: MortarsRate as per item 3.11Sub-analysis | cum | 0.33 | 3,541.40 | 1,168.66 | |
| 0125 | Mason (for plain stone work) 2nd class)Mason (for plain stone work) 2nd classLabour | day | 1.07 | 816.00 | 873.12 |
| 0114 | BeldarLabour | day | 1.07 | 736.00 | 787.52 |
| 0115 | CoolieLabour | day | 0.71 | 736.00 | 522.56 |
| 0101 | BhistiLabour | day | 0.09 | 816.00 | 73.44 |
| 9999 | Cement concrete 1:6:12Material | L.S. | 45.76 | 2.27 | 103.88 |
| 9999 | SundriesMaterial | L.S. | 4.42 | 2.27 | 10.03 |
- TOTAL
- 5,139.21
- Add 1 % Water charges on “W”
- 51.39
- TOTAL
- 5,190.60
- Add GST on “X” (multiplying factor 0.2127)
- 1,104.04
- TOTAL
- 6,294.64
- Add 15% CPOH on “Y”
- 944.20
- TOTAL
- 7,238.84
- Add Cess @ 1% on “Z”
- 72.39
- Cost of 1 cum.
- 7,311.23
- Say
- 7,311.25
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 345. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.