CPWD Analysis of Rates · Stone Work

Extra for laying stone work in or under foul condition

Item number
7.35
Analysis basis
Details of cost for 1 cum.
Priced inputs
4
Derived rate
467.55 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 7.35 Extra for laying stone work in or under foul condition — is derived from 4 priced inputs for 1 cum and works out to ₹467.55 per cum after water charges, GST, CPOH and cess. The full build-up is below.

  • Extra labour due to slow progress-
CodeInputUnitQuantityRate (INR)Amount (INR)
0123Mason 1st classMason 1st classLabourday0.02897.0017.94
0124Mason 2nd classMason 2nd classLabourday0.02816.0016.32
0114BeldarLabourday0.25736.00184.00
0115CoolieLabourday0.15736.00110.40
TOTAL
328.66
Add 1 % Water charges on “W”
3.29
TOTAL
331.95
Add GST on “X” (multiplying factor 0.2127)
70.61
TOTAL
402.56
Add 15% CPOH on “Y”
60.38
TOTAL
462.94
Add Cess @ 1% on “Z”
4.63
Cost for 1 cum.
467.57
Say
467.55

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 377. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.