Extra for laying stone work in or under water and/or liquid mud including cost of pumping or bailing out water and removing slush etc. complete. NOTE :- The quantity will be calculated by multiplying the depth measured from sub-soil water level up to the centre of gravity of stone work under sub - water with the quantity of stone work in cum executed under the sub-soil water. The depth of centre of gravity shall be reckoned correct to 0.1 m, (0.05 m or more shall be taken as 0.1 m and less than 0.05 m ignored)

Item number
7.34
Analysis basis
4.2 cum
Priced inputs
2
Derived rate
₹1,098.80/ CUM
D-01/RATE ANALYSISITEM 7.34

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 7.34 (Extra for laying stone work in or under water and/or liquid mud including cost of pumping or bailing out water and removing slush etc. complete. NOTE :- The quantity will be calculated by multiplying the depth measured from sub-soil water level up to the centre of gravity of stone work under sub - water with the quantity of stone work in cum executed under the sub-soil water. The depth of centre of gravity shall be reckoned correct to 0.1 m, (0.05 m or more shall be taken as 0.1 m and less than 0.05 m ignored)) is derived from 2 priced inputs for 4.2 cum and works out to ₹1,098.80 per cum after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • (14 cum per 0.3m depth)
  • Quantity of concrete = 14 cum.
  • pumping hours = 3 hrs. on 0.375day.
  • for cleaning slush
ANALYSIS OF RATES · ITEM 7.34DETAILS OF COST FOR 4.2 CUM PER 1 M DEPTH
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0011MACHHire charges of Pumpset of capacity 4000 litres/hourHire charges of Pump set of capacity 4000 litres/hourday0.375800.00300.00
0114LABBeldarday4736.002,944.00
BUILD-UP TO RATE
TOTAL
3,244.00
Add 1 % Water charges on “W”
+32.44
TOTAL
3,276.44
Add GST on “X” (multiplying factor 0.2127)
+696.90
TOTAL
3,973.34
Add 15% CPOH on “Y”
+596.00
TOTAL
4,569.34
Add Cess @ 1% on “Z”
+45.69
Cost of 4.2cum per 1 metre depth
4,615.03
Cost of cum per metre depth
1,098.82
SAY
₹1,098.80
D-02/SOURCEPRINTED PAGE 377
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
377

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 377. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSSTONE WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.