Extra for laying stone work in or under water and/or liquid mud including cost of pumping or bailing out water and removing slush etc. complete. NOTE :- The quantity will be calculated by multiplying the depth measured from sub-soil water level up to the centre of gravity of stone work under sub - water with the quantity of stone work in cum executed under the sub-soil water. The depth of centre of gravity shall be reckoned correct to 0.1 m, (0.05 m or more shall be taken as 0.1 m and less than 0.05 m ignored)
- Item number
- 7.34
- Analysis basis
- 4.2 cum
- Priced inputs
- 2
- Derived rate
- ₹1,098.80/ CUM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 7.34 (Extra for laying stone work in or under water and/or liquid mud including cost of pumping or bailing out water and removing slush etc. complete. NOTE :- The quantity will be calculated by multiplying the depth measured from sub-soil water level up to the centre of gravity of stone work under sub - water with the quantity of stone work in cum executed under the sub-soil water. The depth of centre of gravity shall be reckoned correct to 0.1 m, (0.05 m or more shall be taken as 0.1 m and less than 0.05 m ignored)) is derived from 2 priced inputs for 4.2 cum and works out to ₹1,098.80 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- (14 cum per 0.3m depth)
- Quantity of concrete = 14 cum.
- pumping hours = 3 hrs. on 0.375day.
- for cleaning slush
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0011 | MACH | Hire charges of Pumpset of capacity 4000 litres/hourHire charges of Pump set of capacity 4000 litres/hour | day | 0.375 | 800.00 | 300.00 |
| 0114 | LAB | Beldar | day | 4 | 736.00 | 2,944.00 |
- TOTAL
- 3,244.00
- Add 1 % Water charges on “W”
- +32.44
- TOTAL
- 3,276.44
- Add GST on “X” (multiplying factor 0.2127)
- +696.90
- TOTAL
- 3,973.34
- Add 15% CPOH on “Y”
- +596.00
- TOTAL
- 4,569.34
- Add Cess @ 1% on “Z”
- +45.69
- Cost of 4.2cum per 1 metre depth
- 4,615.03
- Cost of cum per metre depth
- 1,098.82
- SAY
- ₹1,098.80
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 377
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 377. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate