Providing and fixing stone jali 40 mm thick throughout in cement mortar 1:3 (1 cement : 3 coarse sand), including pointing in white cement mortar 1:2 (1 white cement : 2 stone dust) with an admixture of pigment, matching the stone shade, jali slab without any chamfers etc

White sand stone
Item number
7.33.2
Analysis basis
1 sqm
Priced inputs
4
Derived rate
₹14,994.15/ SQM
D-01/RATE ANALYSISITEM 7.33.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 7.33.2 (Providing and fixing stone jali 40 mm thick throughout in cement mortar 1:3 (1 cement : 3 coarse sand), including pointing in white cement mortar 1:2 (1 white cement : 2 stone dust) with an admixture of pigment, matching the stone shade, jali slab without any chamfers etc White sand stone) is derived from 4 priced inputs for 1 sqm and works out to ₹14,994.15 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • White sand stone slab 40mm = 1.00
  • sqm. Add 10% wastage = 0.10 sqm. Total
  • = 1.10 sqm.
ANALYSIS OF RATES · ITEM 7.33.2DETAILS OF COST FOR 1 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1165MATWhite sand stone slab 40 mm thick (undressed)White sand stone slab 40 mm thick (un-dressed)sqm1.1370.00407.00
0125LABMason (for plain stone work) 2nd class)Mason (for plain stone work) 2nd classday7.62816.006,217.92
0114LABBeldarday5.07736.003,731.52
9999MATMortar and SundriesL.S.80.732.27183.26
BUILD-UP TO RATE
TOTAL
10,539.70
Add 1 % Water charges on “W”
+105.40
TOTAL
10,645.10
Add GST on “X” (multiplying factor 0.2127)
+2,264.21
TOTAL
12,909.31
Add 15% CPOH on “Y”
+1,936.40
TOTAL
14,845.71
Add Cess @ 1% on “Z”
+148.46
Cost of 1 sqm.
14,994.17
SAY
₹14,994.15
D-02/SOURCEPRINTED PAGE 376
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
376

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 376. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSSTONE WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.