CPWD Analysis of Rates · Stone Work

Providing and fixing stone jali 40 mm thick throughout in cement mortar 1:3 (1 cement : 3 coarse sand), including pointing in white cement mortar 1:2 (1 white cement : 2 stone dust) with an admixture of pigment, matching the stone shade, jali slab without any chamfers etc

White sand stone

Item number
7.33.2
Analysis basis
Details of cost for 1 sqm
Priced inputs
4
Derived rate
14,994.15 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 7.33.2 Providing and fixing stone jali 40 mm thick throughout in cement mortar 1:3 (1 cement : 3 coarse sand), including pointing in white cement mortar 1:2 (1 white cement : 2 stone dust) with an admixture of pigment, matching the stone shade, jali slab without any chamfers etc White sand stone — is derived from 4 priced inputs for 1 sqm and works out to ₹14,994.15 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • White sand stone slab 40mm = 1.00
  • sqm. Add 10% wastage = 0.10 sqm. Total
  • = 1.10 sqm.
CodeInputUnitQuantityRate (INR)Amount (INR)
1165White sand stone slab 40 mm thick (undressed)White sand stone slab 40 mm thick (un-dressed)Materialsqm1.1370.00407.00
0125Mason (for plain stone work) 2nd class)Mason (for plain stone work) 2nd classLabourday7.62816.006,217.92
0114BeldarLabourday5.07736.003,731.52
9999Mortar and SundriesMaterialL.S.80.732.27183.26
TOTAL
10,539.70
Add 1 % Water charges on “W”
105.40
TOTAL
10,645.10
Add GST on “X” (multiplying factor 0.2127)
2,264.21
TOTAL
12,909.31
Add 15% CPOH on “Y”
1,936.40
TOTAL
14,845.71
Add Cess @ 1% on “Z”
148.46
Cost of 1 sqm.
14,994.17
Say
14,994.15

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 376. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.