CPWD Analysis of Rates · Stone Work
Providing and fixing stone jali 40 mm thick throughout in cement mortar 1:3 (1 cement : 3 coarse sand), including pointing in white cement mortar 1:2 (1 white cement : 2 stone dust) with an admixture of pigment, matching the stone shade, jali slab without any chamfers etc
Red sand stone
- Item number
- 7.33.1
- Analysis basis
- Details of cost for 1 sqm
- Priced inputs
- 4
- Derived rate
- ₹14,931.55 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 7.33.1 — Providing and fixing stone jali 40 mm thick throughout in cement mortar 1:3 (1 cement : 3 coarse sand), including pointing in white cement mortar 1:2 (1 white cement : 2 stone dust) with an admixture of pigment, matching the stone shade, jali slab without any chamfers etc Red sand stone — is derived from 4 priced inputs for 1 sqm and works out to ₹14,931.55 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Red sand stone slab 40mm = 1.00 sqm.
- 1.10 sqm.
- Add 10% wastage = 0.10 sqm. Total =
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 1164 | Red sand stone slab 40 mm thick (undressed)Red sand stone slab 40 mm thick (un-dressed)Material | sqm | 1.1 | 330.00 | 363.00 |
| 0125 | Mason (for plain stone work) 2nd class)Mason (for plain stone work) 2nd classLabour | day | 7.62 | 816.00 | 6,217.92 |
| 0114 | BeldarLabour | day | 5.07 | 736.00 | 3,731.52 |
| 9999 | Mortar and SundriesMaterial | L.S. | 80.73 | 2.27 | 183.26 |
- TOTAL
- 10,495.70
- Add 1 % Water charges on “W”
- 104.96
- TOTAL
- 10,600.66
- Add GST on “X” (multiplying factor 0.2127)
- 2,254.76
- TOTAL
- 12,855.42
- Add 15% CPOH on “Y”
- 1,928.31
- TOTAL
- 14,783.73
- Add Cess @ 1% on “Z”
- 147.84
- Cost of 1 sqm.
- 14,931.57
- Say
- 14,931.55
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 376. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.