CPWD Analysis of Rates · Stone Work

Stone work, plain in copings, cornices, string courses and plinth courses, upto 75 mm thick in Cement mortar 1:6 (1 cement : 6 coarse sand), including pointing with white cement mortar

White sand stone

Item number
7.32.2
Analysis basis
Details of cost for 100 cornices (30cm
Priced inputs
4
Derived rate
1,07,965.10 / cornices

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 7.32.2 Stone work, plain in copings, cornices, string courses and plinth courses, upto 75 mm thick in Cement mortar 1:6 (1 cement : 6 coarse sand), including pointing with white cement mortar White sand stone — is derived from 4 priced inputs for 100 cornices and works out to ₹1,07,965.10 per cornices after water charges, GST, CPOH and cess. The full build-up is below.

  • long
  • 30cm deep and 7.5cm project-iron) =
  • 100x6.75cudm = 675 cudm.
  • Stone work plain ashlar cyclopean
  • 100x3x3x0.75 = 675 cudm
  • Extra labour for making the cornices
CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per item no 7.12.1.2 of SH : Stone WorkRate as per item 7.12.1.2Sub-analysiscum0.67582,518.0055,699.65
9999Extra for using white cementMaterialL.S.5332.271,209.91
0125Mason (for plain stone work) 2nd class)Mason (for plain stone work) 2nd classLabourday7816.005,712.00
0114BeldarLabourday7736.005,152.00
TOTAL
67,773.56
Add 1 % Water charges on “W-A”
120.74
TOTAL
67,894.30
Add GST on “X-A” (multiplying factor 0.2127)
2,593.80
TOTAL
70,488.10
Add 15% CPOH on “Y-A”
2,218.27
TOTAL
72,706.37
Add Cess @ 1% on “Z-A”
170.07
Cost of 675 cudm.
72,876.44
Cost per cum.
1,07,965.10
Say
1,07,965.10

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 375. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.