CPWD Analysis of Rates · Stone Work
Stone work, plain in copings, cornices, string courses and plinth courses, upto 75 mm thick in Cement mortar 1:6 (1 cement : 6 coarse sand), including pointing with white cement mortar
White sand stone
- Item number
- 7.32.2
- Analysis basis
- Details of cost for 100 cornices (30cm
- Priced inputs
- 4
- Derived rate
- ₹1,07,965.10 / cornices
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 7.32.2 — Stone work, plain in copings, cornices, string courses and plinth courses, upto 75 mm thick in Cement mortar 1:6 (1 cement : 6 coarse sand), including pointing with white cement mortar White sand stone — is derived from 4 priced inputs for 100 cornices and works out to ₹1,07,965.10 per cornices after water charges, GST, CPOH and cess. The full build-up is below.
- long
- 30cm deep and 7.5cm project-iron) =
- 100x6.75cudm = 675 cudm.
- Stone work plain ashlar cyclopean
- 100x3x3x0.75 = 675 cudm
- Extra labour for making the cornices
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| Rate as per item no 7.12.1.2 of SH : Stone WorkRate as per item 7.12.1.2Sub-analysis | cum | 0.675 | 82,518.00 | 55,699.65 | |
| 9999 | Extra for using white cementMaterial | L.S. | 533 | 2.27 | 1,209.91 |
| 0125 | Mason (for plain stone work) 2nd class)Mason (for plain stone work) 2nd classLabour | day | 7 | 816.00 | 5,712.00 |
| 0114 | BeldarLabour | day | 7 | 736.00 | 5,152.00 |
- TOTAL
- 67,773.56
- Add 1 % Water charges on “W-A”
- 120.74
- TOTAL
- 67,894.30
- Add GST on “X-A” (multiplying factor 0.2127)
- 2,593.80
- TOTAL
- 70,488.10
- Add 15% CPOH on “Y-A”
- 2,218.27
- TOTAL
- 72,706.37
- Add Cess @ 1% on “Z-A”
- 170.07
- Cost of 675 cudm.
- 72,876.44
- Cost per cum.
- 1,07,965.10
- Say
- 1,07,965.10
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 375. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works