Stone work, plain in copings, cornices, string courses and plinth courses, upto 75 mm thick in Cement mortar 1:6 (1 cement : 6 coarse sand), including pointing with white cement mortar

White sand stone
Item number
7.32.2
Analysis basis
100 cornices
Priced inputs
4
Derived rate
₹1,07,965.10/ CORNICES
D-01/RATE ANALYSISITEM 7.32.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 7.32.2 (Stone work, plain in copings, cornices, string courses and plinth courses, upto 75 mm thick in Cement mortar 1:6 (1 cement : 6 coarse sand), including pointing with white cement mortar White sand stone) is derived from 4 priced inputs for 100 cornices and works out to ₹1,07,965.10 per cornices after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • long
  • 30cm deep and 7.5cm project-iron) =
  • 100x6.75cudm = 675 cudm.
  • Stone work plain ashlar cyclopean
  • 100x3x3x0.75 = 675 cudm
  • Extra labour for making the cornices
ANALYSIS OF RATES · ITEM 7.32.2DETAILS OF COST FOR 100 CORNICES (30CM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per item no 7.12.1.2 of SH : Stone WorkRate as per item 7.12.1.2cum0.67582,518.0055,699.65
9999MATExtra for using white cementL.S.5332.271,209.91
0125LABMason (for plain stone work) 2nd class)Mason (for plain stone work) 2nd classday7816.005,712.00
0114LABBeldarday7736.005,152.00
BUILD-UP TO RATE
TOTAL
67,773.56
Add 1 % Water charges on “W-A”
+120.74
TOTAL
67,894.30
Add GST on “X-A” (multiplying factor 0.2127)
+2,593.80
TOTAL
70,488.10
Add 15% CPOH on “Y-A”
+2,218.27
TOTAL
72,706.37
Add Cess @ 1% on “Z-A”
+170.07
Cost of 675 cudm.
72,876.44
Cost per cum.
1,07,965.10
SAY
₹1,07,965.10
D-02/SOURCEPRINTED PAGE 375
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
375

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 375. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.