CPWD Analysis of Rates · Stone Work

Stone work, plain in copings, cornices, string courses and plinth courses, upto 75 mm thick in Cement mortar 1:6 (1 cement : 6 coarse sand), including pointing with white cement mortar

1:2 (1 white cement : 2 stone dust) with an admixture of pigment matching the stone shade. Red sand stone

Item number
7.32.1
Analysis basis
Details of cost for 100 cornices (30cm
Priced inputs
4
Derived rate
93,741.10 / cornices

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 7.32.1 Stone work, plain in copings, cornices, string courses and plinth courses, upto 75 mm thick in Cement mortar 1:6 (1 cement : 6 coarse sand), including pointing with white cement mortar 1:2 (1 white cement : 2 stone dust) with an admixture of pigment matching the stone shade. Red sand stone — is derived from 4 priced inputs for 100 cornices and works out to ₹93,741.10 per cornices after water charges, GST, CPOH and cess. The full build-up is below.

  • long, 30cm deep and 7.5cm project-iron)
  • = 100x6.75cudm = 675 cudm
  • Stone work plain ashlar cyclopean
  • 100x3x3x0.75 = 675 cudm
  • Extra labour for making the cornices
CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per item no 7.12.1.1 of SH : Stone WorkRate as per item 7.12.1.1Sub-analysiscum0.67568,294.0046,098.45
9999Extra for using white cementMaterialL.S.5332.271,209.91
0125Mason (for plain stone work) 2nd class)Mason (for plain stone work) 2nd classLabourday7816.005,712.00
0114BeldarLabourday7736.005,152.00
TOTAL
58,172.36
Add 1 % Water charges on “W-A”
120.74
TOTAL
58,293.10
Add GST on “X-A” (multiplying factor 0.2127)
2,593.80
TOTAL
60,886.90
Add 15% CPOH on “Y-A”
2,218.27
TOTAL
63,105.17
Add Cess @ 1% on “Z-A”
170.07
Cost of 675 cudm
63,275.24
Cost per cum.
93,741.10
Say
93,741.10

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 375. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.