Providing and fixing red sand stone brackets 55x22.5x45 cm sunk and moulded including providing and fixing with 4 Nos gun metal cramp 25x6 mm 30 cm long
- Item number
- 7.31
- Analysis basis
- 10 brackets
- Priced inputs
- 16
- Derived rate
- ₹6,788.85/ BRACKETS
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 7.31 (Providing and fixing red sand stone brackets 55x22.5x45 cm sunk and moulded including providing and fixing with 4 Nos gun metal cramp 25x6 mm 30 cm long) is derived from 16 priced inputs for 10 brackets and works out to ₹6,788.85 per brackets after water charges, GST, CPOH and cess. The full build-up is below.
- Quantity of stone for 10 brackets
- 10x 0.55 x 0.225 x 0.45m = 0.560 cum or
- 560 cudm.
- Red sand stone = 560 cudm.
- Total = 616 cudm.
- Fixing charges
- Extra labour for ornamental finish :
- Add wastage 10% = 56 cudm.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 1160 | MAT | Red sand stone block | 10 cudm | 61.6 | 130.00 | 8,008.00 |
| 0125 | LAB | Mason (for plain stone work) 2nd class)Mason (for plain stone work) 2nd class | day | 17.926 | 816.00 | 14,627.62 |
| 0102 | LAB | Blacksmith 1st class | day | 0.37 | 897.00 | 331.89 |
| 0114 | LAB | Beldar | day | 2.71 | 736.00 | 1,994.56 |
| 0115 | LAB | Coolie | day | 1.355 | 736.00 | 997.28 |
| 0100 | LAB | Bandhani | day | 2.71 | 816.00 | 2,211.36 |
| 0373 | MAT | Cramp Gun metal 25x6x300 mm | each | 40 | 88.00 | 3,520.00 |
| 0125 | LAB | Mason (for plain stone work) 2nd class)Mason (for plain stone work) 2nd class | day | 2.464 | 816.00 | 2,010.62 |
| 0102 | LAB | Blacksmith 1st class | day | 0.336 | 897.00 | 301.39 |
| 0114 | LAB | Beldar | day | 1.232 | 736.00 | 906.75 |
| 0115 | LAB | Coolie | day | 1.232 | 736.00 | 906.75 |
| 0100 | LAB | Bandhani | day | 1.232 | 816.00 | 1,005.31 |
| 0101 | LAB | Bhisti | day | 1.232 | 816.00 | 1,005.31 |
| 9999 | MAT | Scaffolding | L.S. | 152.9 | 2.27 | 347.08 |
| 9999 | MAT | Mortar for laying and pointing | L.S. | 451.4 | 2.27 | 1,024.68 |
| 0126 | LAB | Mason (for ornamental stone work) 1st class | day | 9.5 | 897.00 | 8,521.50 |
- TOTAL
- 47,720.10
- Add 1 % Water charges on “W”
- +477.20
- TOTAL
- 48,197.30
- Add GST on “X” (multiplying factor 0.2127)
- +10,251.57
- TOTAL
- 58,448.87
- Add 15% CPOH on “Y”
- +8,767.33
- TOTAL
- 67,216.20
- Add Cess @ 1% on “Z”
- +672.16
- Cost of 10 Bracket
- 67,888.36
- Cost for 1 Bracket
- 6,788.84
- SAY
- ₹6,788.85
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 374
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 374. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.