CPWD Analysis of Rates · Stone Work
Providing and fixing red sand stone brackets 55x22.5x45 cm sunk and moulded including providing and fixing with 4 Nos gun metal cramp 25x6 mm 30 cm long
- Item number
- 7.31
- Analysis basis
- Details of cost for 10 brackets
- Priced inputs
- 16
- Derived rate
- ₹6,788.85 / brackets
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 7.31 — Providing and fixing red sand stone brackets 55x22.5x45 cm sunk and moulded including providing and fixing with 4 Nos gun metal cramp 25x6 mm 30 cm long — is derived from 16 priced inputs for 10 brackets and works out to ₹6,788.85 per brackets after water charges, GST, CPOH and cess. The full build-up is below.
- Quantity of stone for 10 brackets
- 10x 0.55 x 0.225 x 0.45m = 0.560 cum or
- 560 cudm.
- Red sand stone = 560 cudm.
- Total = 616 cudm.
- Fixing charges
- Extra labour for ornamental finish :
- Add wastage 10% = 56 cudm.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 1160 | Red sand stone blockMaterial | 10 cudm | 61.6 | 130.00 | 8,008.00 |
| 0125 | Mason (for plain stone work) 2nd class)Mason (for plain stone work) 2nd classLabour | day | 17.926 | 816.00 | 14,627.62 |
| 0102 | Blacksmith 1st classLabour | day | 0.37 | 897.00 | 331.89 |
| 0114 | BeldarLabour | day | 2.71 | 736.00 | 1,994.56 |
| 0115 | CoolieLabour | day | 1.355 | 736.00 | 997.28 |
| 0100 | BandhaniLabour | day | 2.71 | 816.00 | 2,211.36 |
| 0373 | Cramp Gun metal 25x6x300 mmMaterial | each | 40 | 88.00 | 3,520.00 |
| 0125 | Mason (for plain stone work) 2nd class)Mason (for plain stone work) 2nd classLabour | day | 2.464 | 816.00 | 2,010.62 |
| 0102 | Blacksmith 1st classLabour | day | 0.336 | 897.00 | 301.39 |
| 0114 | BeldarLabour | day | 1.232 | 736.00 | 906.75 |
| 0115 | CoolieLabour | day | 1.232 | 736.00 | 906.75 |
| 0100 | BandhaniLabour | day | 1.232 | 816.00 | 1,005.31 |
| 0101 | BhistiLabour | day | 1.232 | 816.00 | 1,005.31 |
| 9999 | ScaffoldingMaterial | L.S. | 152.9 | 2.27 | 347.08 |
| 9999 | Mortar for laying and pointingMaterial | L.S. | 451.4 | 2.27 | 1,024.68 |
| 0126 | Mason (for ornamental stone work) 1st classLabour | day | 9.5 | 897.00 | 8,521.50 |
- TOTAL
- 47,720.10
- Add 1 % Water charges on “W”
- 477.20
- TOTAL
- 48,197.30
- Add GST on “X” (multiplying factor 0.2127)
- 10,251.57
- TOTAL
- 58,448.87
- Add 15% CPOH on “Y”
- 8,767.33
- TOTAL
- 67,216.20
- Add Cess @ 1% on “Z”
- 672.16
- Cost of 10 Bracket
- 67,888.36
- Cost for 1 Bracket
- 6,788.84
- Say
- 6,788.85
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 374. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works