Providing and fixing red sand stone brackets 55x22.5x45 cm sunk and moulded including providing and fixing with 4 Nos gun metal cramp 25x6 mm 30 cm long

Item number
7.31
Analysis basis
10 brackets
Priced inputs
16
Derived rate
₹6,788.85/ BRACKETS
D-01/RATE ANALYSISITEM 7.31

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 7.31 (Providing and fixing red sand stone brackets 55x22.5x45 cm sunk and moulded including providing and fixing with 4 Nos gun metal cramp 25x6 mm 30 cm long) is derived from 16 priced inputs for 10 brackets and works out to ₹6,788.85 per brackets after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Quantity of stone for 10 brackets
  • 10x 0.55 x 0.225 x 0.45m = 0.560 cum or
  • 560 cudm.
  • Red sand stone = 560 cudm.
  • Total = 616 cudm.
  • Fixing charges
  • Extra labour for ornamental finish :
  • Add wastage 10% = 56 cudm.
ANALYSIS OF RATES · ITEM 7.31DETAILS OF COST FOR 10 BRACKETS
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1160MATRed sand stone block10 cudm61.6130.008,008.00
0125LABMason (for plain stone work) 2nd class)Mason (for plain stone work) 2nd classday17.926816.0014,627.62
0102LABBlacksmith 1st classday0.37897.00331.89
0114LABBeldarday2.71736.001,994.56
0115LABCoolieday1.355736.00997.28
0100LABBandhaniday2.71816.002,211.36
0373MATCramp Gun metal 25x6x300 mmeach4088.003,520.00
0125LABMason (for plain stone work) 2nd class)Mason (for plain stone work) 2nd classday2.464816.002,010.62
0102LABBlacksmith 1st classday0.336897.00301.39
0114LABBeldarday1.232736.00906.75
0115LABCoolieday1.232736.00906.75
0100LABBandhaniday1.232816.001,005.31
0101LABBhistiday1.232816.001,005.31
9999MATScaffoldingL.S.152.92.27347.08
9999MATMortar for laying and pointingL.S.451.42.271,024.68
0126LABMason (for ornamental stone work) 1st classday9.5897.008,521.50
BUILD-UP TO RATE
TOTAL
47,720.10
Add 1 % Water charges on “W”
+477.20
TOTAL
48,197.30
Add GST on “X” (multiplying factor 0.2127)
+10,251.57
TOTAL
58,448.87
Add 15% CPOH on “Y”
+8,767.33
TOTAL
67,216.20
Add Cess @ 1% on “Z”
+672.16
Cost of 10 Bracket
67,888.36
Cost for 1 Bracket
6,788.84
SAY
₹6,788.85
D-02/SOURCEPRINTED PAGE 374
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
374

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 374. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSSTONE WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.