CPWD Analysis of Rates · Stone Work
30 mm red sand stone sun-shade (chisel-dressed) supported on red sand stone brackets, fixed in walls with cement mortar 1:4 (1 cement : 4 coarse sand), including finishing complete
- Item number
- 7.30
- Analysis basis
- Detail of cost for window 1.6m length and
- Priced inputs
- 4
- Derived rate
- ₹2,159.90 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 7.30 — 30 mm red sand stone sun-shade (chisel-dressed) supported on red sand stone brackets, fixed in walls with cement mortar 1:4 (1 cement : 4 coarse sand), including finishing complete — is derived from 4 priced inputs for window 1 and works out to ₹2,159.90 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- 0.70m width = 1.12 sqm.
- over all width 0.70+0.15=0.85 metres
- Total area = 1.6x0.85=1.36sqm.
- Red stone brackets (chisel dressed)
- 30mm average thickness over all width of
- brackets
- 0.53+0.23=0.76m
- 2x0.3x0.76=0.46
- Total 1.36+0.46 =1.82sqm.+
- Total = 2.00 sqm.
- Labour for dressing and fixing:
- Add wastage @10% = 0.18sqm.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 1166 | Red sand stone slab 30 mmthick (undressed)Red sand stone slab 30 mm thick (un-dressed)Material | sqm | 2 | 300.00 | 600.00 |
| 9999 | Cement mortar 1 :4Material | L.S. | 13.52 | 2.27 | 30.69 |
| 0125 | Mason (for plain stone work) 2nd class)Mason (for plain stone work) 2nd classLabour | day | 0.86 | 816.00 | 701.76 |
| 0114 | BeldarLabour | day | 0.5 | 736.00 | 368.00 |
- TOTAL
- 1,700.45
- Add 1 % Water charges on “W”
- 17.00
- TOTAL
- 1,717.45
- Add GST on “X” (multiplying factor 0.2127)
- 365.30
- TOTAL
- 2,082.75
- Add 15% CPOH on “Y”
- 312.41
- TOTAL
- 2,395.16
- Add Cess @ 1% on “Z”
- 23.95
- Cost for 1.12 sqm.
- 2,419.11
- Cost of 1 sqm.
- 2,159.92
- Say
- 2,159.90
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 373. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.