Extra for stone work (veneer work) curved on plan with a mean radius not exceeding 6 m

Item number
7.24
Analysis basis
10 cudm
Priced inputs
1
Derived rate
₹2,896.00/ CUM
D-01/RATE ANALYSISITEM 7.24

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 7.24 (Extra for stone work (veneer work) curved on plan with a mean radius not exceeding 6 m) is derived from 1 priced inputs for 10 cudm and works out to ₹2,896.00 per cum after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 7.24DETAILS OF COST FOR 10 CUDM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
9999MATLabour and materialsL.S.8.972.2720.36
BUILD-UP TO RATE
TOTAL
20.36
Add 1 % Water charges on “W”
+0.20
TOTAL
20.56
Add GST on “X” (multiplying factor 0.2127)
+4.37
TOTAL
24.93
Add 15% CPOH on “Y”
+3.74
TOTAL
28.67
Add Cess @ 1% on “Z”
+0.29
Cost of 10 cudm.
28.96
Cost of 1 cum.
2,896.00
SAY
₹2,896.00
D-02/SOURCEPRINTED PAGE 369
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
369

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 369. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.