Extra for stone work ashlar sunk or moulded in cornices
- Item number
- 7.22
- Analysis basis
- a cornice
- Priced inputs
- 2
- Derived rate
- ₹303.50/ A CORNICE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 7.22 (Extra for stone work ashlar sunk or moulded in cornices) is derived from 2 priced inputs for a cornice and works out to ₹303.50 per a cornice after water charges, GST, CPOH and cess. The full build-up is below.
- 60cm deep and 15cm projection
- Extra labour :
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0125 | LAB | Mason (for plain stone work) 2nd class)Mason (for plain stone work) 2nd class | day | 0.5 | 816.00 | 408.00 |
| 0114 | LAB | Beldar | day | 0.75 | 736.00 | 552.00 |
- TOTAL
- 960.00
- Add 1 % Water charges on “W”
- +9.60
- TOTAL
- 969.60
- Add GST on “X” (multiplying factor 0.2127)
- +206.23
- TOTAL
- 1,175.83
- Add 15% CPOH on “Y”
- +176.37
- TOTAL
- 1,352.20
- Add Cess @ 1% on “Z”
- +13.52
- Cost of 30cm long 60cm deep and 15cm girth
- 1,365.72
- Cost of per metre per cm girth (60cm deep)
- 303.49
- SAY
- ₹303.50
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 369
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 369. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate