CPWD Analysis of Rates · Stone Work
Extra for stone work ashlar sunk or moulded in cornices
- Item number
- 7.22
- Analysis basis
- Details of cost for a cornice 30cm long,
- Priced inputs
- 2
- Derived rate
- ₹303.50 / a cornice
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 7.22 — Extra for stone work ashlar sunk or moulded in cornices — is derived from 2 priced inputs for a cornice and works out to ₹303.50 per a cornice after water charges, GST, CPOH and cess. The full build-up is below.
- 60cm deep and 15cm projection
- Extra labour :
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0125 | Mason (for plain stone work) 2nd class)Mason (for plain stone work) 2nd classLabour | day | 0.5 | 816.00 | 408.00 |
| 0114 | BeldarLabour | day | 0.75 | 736.00 | 552.00 |
- TOTAL
- 960.00
- Add 1 % Water charges on “W”
- 9.60
- TOTAL
- 969.60
- Add GST on “X” (multiplying factor 0.2127)
- 206.23
- TOTAL
- 1,175.83
- Add 15% CPOH on “Y”
- 176.37
- TOTAL
- 1,352.20
- Add Cess @ 1% on “Z”
- 13.52
- Cost of 30cm long 60cm deep and 15cm girth
- 1,365.72
- Cost of per metre per cm girth (60cm deep)
- 303.49
- Say
- 303.50
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 369. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works