Skip to main content
R/DAR 2023

Extra for stone work ashlar sunk or moulded in cornices

Item number
7.22
Analysis basis
a cornice
Priced inputs
2
Derived rate
₹303.50/ A CORNICE
D-01/RATE ANALYSISITEM 7.22

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 7.22 (Extra for stone work ashlar sunk or moulded in cornices) is derived from 2 priced inputs for a cornice and works out to ₹303.50 per a cornice after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 60cm deep and 15cm projection
  • Extra labour :
ANALYSIS OF RATES · ITEM 7.22DETAILS OF COST FOR A CORNICE 30CM LONG,
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0125LABMason (for plain stone work) 2nd class)Mason (for plain stone work) 2nd classday0.5816.00408.00
0114LABBeldarday0.75736.00552.00
BUILD-UP TO RATE
TOTAL
960.00
Add 1 % Water charges on “W”
+9.60
TOTAL
969.60
Add GST on “X” (multiplying factor 0.2127)
+206.23
TOTAL
1,175.83
Add 15% CPOH on “Y”
+176.37
TOTAL
1,352.20
Add Cess @ 1% on “Z”
+13.52
Cost of 30cm long 60cm deep and 15cm girth
1,365.72
Cost of per metre per cm girth (60cm deep)
303.49
SAY
₹303.50
D-02/SOURCEPRINTED PAGE 369
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
369

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 369. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSSTONE WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.