Skip to main content

CPWD Analysis of Rates · Stone Work

Extra for stone work ashlar sunk or moulded or sunk and moulded or carved in

Circular or polygonal pillars

Item number
7.21.2
Analysis basis
Details of cost for 10 cudm or 0.01 cum
Priced inputs
1
Derived rate
10,706.00 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 7.21.2 Extra for stone work ashlar sunk or moulded or sunk and moulded or carved in : Circular or polygonal pillars — is derived from 1 priced inputs for 10 cudm and works out to ₹10,706.00 per cum after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
9999LABOURMaterialL.S.33.152.2775.25
TOTAL
75.25
Add 1 % Water charges on “W”
0.75
TOTAL
76.00
Add GST on “X” (multiplying factor 0.2127)
16.17
TOTAL
92.17
Add 15% CPOH on “Y”
13.83
TOTAL
106.00
Add Cess @ 1% on “Z”
1.06
Cost of 10 cudm.
107.06
Cost of 1 cum.
10,706.00
Say
10,706.00

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 369. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works