CPWD Analysis of Rates · Stone Work
Extra for stone work ashlar sunk or moulded or sunk and moulded or carved in
Circular or polygonal pillars
- Item number
- 7.21.2
- Analysis basis
- Details of cost for 10 cudm or 0.01 cum
- Priced inputs
- 1
- Derived rate
- ₹10,706.00 / cum
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 7.21.2 — Extra for stone work ashlar sunk or moulded or sunk and moulded or carved in : Circular or polygonal pillars — is derived from 1 priced inputs for 10 cudm and works out to ₹10,706.00 per cum after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 9999 | LABOURMaterial | L.S. | 33.15 | 2.27 | 75.25 |
- TOTAL
- 75.25
- Add 1 % Water charges on “W”
- 0.75
- TOTAL
- 76.00
- Add GST on “X” (multiplying factor 0.2127)
- 16.17
- TOTAL
- 92.17
- Add 15% CPOH on “Y”
- 13.83
- TOTAL
- 106.00
- Add Cess @ 1% on “Z”
- 1.06
- Cost of 10 cudm.
- 107.06
- Cost of 1 cum.
- 10,706.00
- Say
- 10,706.00
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 369. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works