Extra for stone work ashlar sunk or moulded or sunk and moulded or carved in

Triangular or Square or rectangular pillars
Item number
7.21.1
Analysis basis
10 cudm
Priced inputs
1
Derived rate
₹3,779.00/ CUM
D-01/RATE ANALYSISITEM 7.21.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 7.21.1 (Extra for stone work ashlar sunk or moulded or sunk and moulded or carved in : Triangular or Square or rectangular pillars) is derived from 1 priced inputs for 10 cudm and works out to ₹3,779.00 per cum after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 7.21.1DETAILS OF COST FOR 10 CUDM OR 0.01 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
9999MATLABOURL.S.11.72.2726.56
BUILD-UP TO RATE
TOTAL
26.56
Add 1 % Water charges on “W”
+0.27
TOTAL
26.83
Add GST on “X” (multiplying factor 0.2127)
+5.71
TOTAL
32.54
Add 15% CPOH on “Y”
+4.88
TOTAL
37.42
Add Cess @ 1% on “Z”
+0.37
Cost of 10 cudm.
37.79
Cost of 1 cum.
3,779.00
SAY
₹3,779.00
D-02/SOURCEPRINTED PAGE 368
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
368

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 368. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.