Extra for stone work ashlar sunk or moulded or sunk and moulded or carved in

Triangular or Square or rectangular pillars

Item number
7.21.1
Analysis basis
Details of cost for 10 cudm or 0.01 cum
Priced inputs
1
Derived rate
3,779.00 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 7.21.1 Extra for stone work ashlar sunk or moulded or sunk and moulded or carved in : Triangular or Square or rectangular pillars — is derived from 1 priced inputs for 10 cudm and works out to ₹3,779.00 per cum after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
9999LABOURMaterialL.S.11.72.2726.56
TOTAL
26.56
Add 1 % Water charges on “W”
0.27
TOTAL
26.83
Add GST on “X” (multiplying factor 0.2127)
5.71
TOTAL
32.54
Add 15% CPOH on “Y”
4.88
TOTAL
37.42
Add Cess @ 1% on “Z”
0.37
Cost of 10 cudm.
37.79
Cost of 1 cum.
3,779.00
Say
3,779.00

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 368. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works