Stone work ashlar sunk or moulded or sunk and moulded upto floor five level in cement mortar

White sand stone

Item number
7.20.2
Analysis basis
Details of cost for 10 cudm or 0.01 cum
Priced inputs
16
Derived rate
1,08,686.00 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 7.20.2 Stone work ashlar sunk or moulded or sunk and moulded upto floor five level in cement mortar White sand stone — is derived from 16 priced inputs for 10 cudm and works out to ₹1,08,686.00 per cum after water charges, GST, CPOH and cess. The full build-up is below.

  • Finished work = 10 cudm.+ Add wastage
  • @ 33.3% = 3.33 cudm. Total = 13.33
  • cudm.
  • Dressing charges
  • Fixing charges
  • Extra labour for lifting of materials upto
  • floor V level (0.01x1.50=0.015)
CodeInputUnitQuantityRate (INR)Amount (INR)
1161White sand stone blockMaterial10 cudm1.333205.00273.27
9999Extra for using white cementMaterialL.S.8.062.2718.30
0125Mason (for plain stone work) 2nd class)Mason (for plain stone work) 2nd classLabourday0.291816.00237.46
0102Blacksmith 1st classLabourday0.006897.005.38
0114BeldarLabourday0.044736.0032.38
0115CoolieLabourday0.022736.0016.19
0100BandhaniLabourday0.044816.0035.90
0125Mason (for plain stone work) 2nd class)Mason (for plain stone work) 2nd classLabourday0.044816.0035.90
0102Blacksmith 1st classLabourday0.006897.005.38
0114BeldarLabourday0.022736.0016.19
0115CoolieLabourday0.022736.0016.19
0100BandhaniLabourday0.022816.0017.95
0101BhistiLabourday0.022816.0017.95
9999ScaffoldingMaterialL.S.2.732.276.20
9999Mortar for laying and pointingMaterialL.S.8.062.2718.30
0115CoolieLabourday0.015736.0011.04
TOTAL
763.98
Add 1 % Water charges on “W”
7.64
TOTAL
771.62
Add GST on “X” (multiplying factor 0.2127)
164.12
TOTAL
935.74
Add 15% CPOH on “Y”
140.36
TOTAL
1,076.10
Add Cess @ 1% on “Z”
10.76
Cost of 10 cudm.
1,086.86
Cost of 1 cum.
1,08,686.00
Say
1,08,686.00

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 367. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.