CPWD Analysis of Rates · Stone Work
Stone work ashlar sunk or moulded or sunk and moulded upto floor five level in cement mortar
1:6 (1 cement : 6 coarse sand) including pointing with white cement mortar 1:2 (1 white cement : 2 stone dust) with an admixture of pigment matching the stone shade : Red sand stone
- Item number
- 7.20.1
- Analysis basis
- Details of cost for 10 cudm or 0.01 cum
- Priced inputs
- 16
- Derived rate
- ₹94,463.00 / cum
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 7.20.1 — Stone work ashlar sunk or moulded or sunk and moulded upto floor five level in cement mortar 1:6 (1 cement : 6 coarse sand) including pointing with white cement mortar 1:2 (1 white cement : 2 stone dust) with an admixture of pigment matching the stone shade : Red sand stone — is derived from 16 priced inputs for 10 cudm and works out to ₹94,463.00 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- Finished work = 10 cudm + Add wastage
- @ 33.3% = 3.33 cudm. Total = 13.33
- cudm.
- Dressing charges
- Fixing charges
- Extra labour for lifting of materials upto
- floor V level (0.01x1.50=0.015)
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 1160 | Red sand stone blockMaterial | 10 cudm | 1.333 | 130.00 | 173.29 |
| 9999 | Extra for using white cementMaterial | L.S. | 8.06 | 2.27 | 18.30 |
| 0125 | Mason (for plain stone work) 2nd class)Mason (for plain stone work) 2nd classLabour | day | 0.291 | 816.00 | 237.46 |
| 0102 | Blacksmith 1st classLabour | day | 0.006 | 897.00 | 5.38 |
| 0114 | BeldarLabour | day | 0.044 | 736.00 | 32.38 |
| 0115 | CoolieLabour | day | 0.022 | 736.00 | 16.19 |
| 0100 | BandhaniLabour | day | 0.044 | 816.00 | 35.90 |
| 0125 | Mason (for plain stone work) 2nd classLabour | day | 0.044 | 816.00 | 35.90 |
| 0102 | Blacksmith 1st classLabour | day | 0.006 | 897.00 | 5.38 |
| 0114 | BeldarLabour | day | 0.022 | 736.00 | 16.19 |
| 0115 | CoolieLabour | day | 0.022 | 736.00 | 16.19 |
| 0100 | BandhaniLabour | day | 0.022 | 816.00 | 17.95 |
| 0101 | BhistiLabour | day | 0.022 | 816.00 | 17.95 |
| 9999 | ScaffoldingMaterial | L.S. | 2.73 | 2.27 | 6.20 |
| 9999 | Mortar for laying and pointingMaterial | L.S. | 8.06 | 2.27 | 18.30 |
| 0115 | CoolieLabour | day | 0.015 | 736.00 | 11.04 |
- TOTAL
- 664.00
- Add 1 % Water charges on “W”
- 6.64
- TOTAL
- 670.64
- Add GST on “X” (multiplying factor 0.2127)
- 142.65
- TOTAL
- 813.29
- Add 15% CPOH on “Y”
- 121.99
- TOTAL
- 935.28
- Add Cess @ 1% on “Z”
- 9.35
- Cost of 10 cudm.
- 944.63
- Cost of 1 cum.
- 94,463.00
- Say
- 94,463.00
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 367. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.