Skip to main content
R/DAR 2023

Providing and fixing stone dowels 10x5x2.50 cm cut to double wedge shape as per design in cement mortar 1:2 (1 cement : 2 coarse sand), including making the necessary chases

Item number
7.26
Analysis basis
one dowel
Priced inputs
3
Derived rate
₹54.55/ ONE DOWEL
D-01/RATE ANALYSISITEM 7.26

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 7.26 (Providing and fixing stone dowels 10x5x2.50 cm cut to double wedge shape as per design in cement mortar 1:2 (1 cement : 2 coarse sand), including making the necessary chases) is derived from 3 priced inputs for one dowel and works out to ₹54.55 per one dowel after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Cement mortar 1:2 (1 cement : 2 coarse
  • sand)
ANALYSIS OF RATES · ITEM 7.26DETAILS OF COST FOR ONE DOWEL
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
9999MATCost of stone including carriageL.S.9.12.2720.66
9999MATLabour for dressing dowel cutting chase and fixing etcL.S.5.332.2712.10
SUBRate as per Item Number 3.7 of SH: MortarsRate as per item 3.7cum0.0015,584.505.58
BUILD-UP TO RATE
TOTAL
38.34
Add 1 % Water charges on “W”
+0.38
TOTAL
38.72
Add GST on “X” (multiplying factor 0.2127)
+8.24
TOTAL
46.96
Add 15% CPOH on “Y”
+7.04
TOTAL
54.00
Add Cess @ 1% on “Z”
+0.54
Cost of each dowel
54.54
SAY
₹54.55
D-02/SOURCEPRINTED PAGE 370
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
370

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 370. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSSTONE WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.