Providing and fixing stone dowels 10x5x2.50 cm cut to double wedge shape as per design in cement mortar 1:2 (1 cement : 2 coarse sand), including making the necessary chases
- Item number
- 7.26
- Analysis basis
- one dowel
- Priced inputs
- 3
- Derived rate
- ₹54.55/ ONE DOWEL
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 7.26 (Providing and fixing stone dowels 10x5x2.50 cm cut to double wedge shape as per design in cement mortar 1:2 (1 cement : 2 coarse sand), including making the necessary chases) is derived from 3 priced inputs for one dowel and works out to ₹54.55 per one dowel after water charges, GST, CPOH and cess. The full build-up is below.
- Cement mortar 1:2 (1 cement : 2 coarse
- sand)
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 9999 | MAT | Cost of stone including carriage | L.S. | 9.1 | 2.27 | 20.66 |
| 9999 | MAT | Labour for dressing dowel cutting chase and fixing etc | L.S. | 5.33 | 2.27 | 12.10 |
| SUB | Rate as per Item Number 3.7 of SH: MortarsRate as per item 3.7 | cum | 0.001 | 5,584.50 | 5.58 |
- TOTAL
- 38.34
- Add 1 % Water charges on “W”
- +0.38
- TOTAL
- 38.72
- Add GST on “X” (multiplying factor 0.2127)
- +8.24
- TOTAL
- 46.96
- Add 15% CPOH on “Y”
- +7.04
- TOTAL
- 54.00
- Add Cess @ 1% on “Z”
- +0.54
- Cost of each dowel
- 54.54
- SAY
- ₹54.55
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 370
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 370. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.