Skip to main content

CPWD Analysis of Rates · Stone Work

Stone work ashlar punched (ordinary) in superstructure upto floor five level in cement mortar Both faced punched

White sand stone

Item number
7.15.2.2
Analysis basis
Details of cost for 10 cudm or 0.01 cum
Priced inputs
15
Derived rate
98,784.00 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 7.15.2.2 Stone work ashlar punched (ordinary) in superstructure upto floor five level in cement mortar Both faced punched White sand stone — is derived from 15 priced inputs for 10 cudm and works out to ₹98,784.00 per cum after water charges, GST, CPOH and cess. The full build-up is below.

  • Finished work = 10 cudm. Add wastage
  • @ 33.3% = 3.33 cudm. Total = 13.33
  • cudm.
  • Extra labour for lifting of materials upto
  • floor V level (0.01x1.50 = 0.015)
  • Dressing charges
  • Fixing charges
CodeInputUnitQuantityRate (INR)Amount (INR)
1161White sand stone blockMaterial10 cudm1.333205.00273.27
0115CoolieLabourday0.015736.0011.04
0125Mason (for plain stone work) 2nd class)Mason (for plain stone work) 2nd classLabourday0.118816.0096.29
0102Blacksmith 1st classLabourday0.012897.0010.76
0114BeldarLabourday0.088736.0064.77
0115CoolieLabourday0.044736.0032.38
0100BandhaniLabourday0.088816.0071.81
0125Mason (for plain stone work) 2nd classLabourday0.044816.0035.90
0102Blacksmith 1st classLabourday0.006897.005.38
0114BeldarLabourday0.022736.0016.19
0115CoolieLabourday0.022736.0016.19
0100BandhaniLabourday0.022816.0017.95
0101BhistiLabourday0.022816.0017.95
9999ScaffoldingMaterialL.S.2.732.276.20
9999Mortar for laying and pointingMaterialL.S.8.062.2718.30
TOTAL
694.38
Add 1 % Water charges on “W”
6.94
TOTAL
701.32
Add GST on “X” (multiplying factor 0.2127)
149.17
TOTAL
850.49
Add 15% CPOH on “Y”
127.57
TOTAL
978.06
Add Cess @ 1% on “Z”
9.78
Cost of 10 cudm.
987.84
Cost of 1 cum.
98,784.00
Say
98,784.00

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 363. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works