CPWD Analysis of Rates · Stone Work

Extra for stone work, random rubble / coursed rubble masonry / ashlar masonry above floor V level for every four floors or part thereof by mechnical means

Item number
7.16
Analysis basis
Details of cost for 5.3 cum per four floors .
Priced inputs
1
Derived rate
169.45 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 7.16 Extra for stone work, random rubble / coursed rubble masonry / ashlar masonry above floor V level for every four floors or part thereof by mechnical means — is derived from 1 priced inputs for 5.3 cum and works out to ₹169.45 per cum after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
0037Mobile craneMachineryday0.1255,050.00631.25
TOTAL
631.25
Add 1 % Water charges on “W”
6.31
TOTAL
637.56
Add GST on “X” (multiplying factor 0.2127)
135.61
TOTAL
773.17
Add 15% CPOH on “Y”
115.98
TOTAL
889.15
Add Cess @ 1% on “Z”
8.89
Cost of 5.3 Cum.
898.04
Cost for 1 cum
169.44
Say
169.45

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 364. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.