Extra for stone work, random rubble / coursed rubble masonry / ashlar masonry above floor V level for every four floors or part thereof by mechnical means

Item number
7.16
Analysis basis
5.3 cum
Priced inputs
1
Derived rate
₹169.45/ CUM
D-01/RATE ANALYSISITEM 7.16

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 7.16 (Extra for stone work, random rubble / coursed rubble masonry / ashlar masonry above floor V level for every four floors or part thereof by mechnical means) is derived from 1 priced inputs for 5.3 cum and works out to ₹169.45 per cum after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 7.16DETAILS OF COST FOR 5.3 CUM PER FOUR FLOORS
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0037MACHMobile craneday0.1255,050.00631.25
BUILD-UP TO RATE
TOTAL
631.25
Add 1 % Water charges on “W”
+6.31
TOTAL
637.56
Add GST on “X” (multiplying factor 0.2127)
+135.61
TOTAL
773.17
Add 15% CPOH on “Y”
+115.98
TOTAL
889.15
Add Cess @ 1% on “Z”
+8.89
Cost of 5.3 Cum.
898.04
Cost for 1 cum
169.44
SAY
₹169.45
D-02/SOURCEPRINTED PAGE 364
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
364

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 364. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSSTONE WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.