Stone work ashlar punched (ordinary) in superstructure upto floor five level in cement mortar Both faced punched

Red sand stone

Item number
7.15.2.1
Analysis basis
Details of cost for 10 cudm or 0.01 cum
Priced inputs
15
Derived rate
84,560.00 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 7.15.2.1 Stone work ashlar punched (ordinary) in superstructure upto floor five level in cement mortar Both faced punched Red sand stone — is derived from 15 priced inputs for 10 cudm and works out to ₹84,560.00 per cum after water charges, GST, CPOH and cess. The full build-up is below.

  • Finished work = 10 cudm. Add wastage
  • @ 33.3% = 3.33 cudm. Total = 13.33
  • cudm
  • Extra labour for lifting of materials upto
  • floor V level (0.01x1.50 = 0.015)
  • Dressing charges
  • Fixing charges
CodeInputUnitQuantityRate (INR)Amount (INR)
1160Red sand stone blockMaterial10 cudm1.333130.00173.29
0115CoolieLabourday0.015736.0011.04
0125Mason (for plain stone work) 2nd class)Mason (for plain stone work) 2nd classLabourday0.118816.0096.29
0102Blacksmith 1st classLabourday0.012897.0010.76
0114BeldarLabourday0.088736.0064.77
0115CoolieLabourday0.044736.0032.38
0100BandhaniLabourday0.088816.0071.81
0125Mason (for plain stone work) 2nd class)Mason (for plain stone work) 2nd classLabourday0.044816.0035.90
0102Blacksmith 1st classLabourday0.006897.005.38
0114BeldarLabourday0.022736.0016.19
0115CoolieLabourday0.022736.0016.19
0100BandhaniLabourday0.022816.0017.95
0101BhistiLabourday0.022816.0017.95
9999ScafoldingMaterialL.S.2.732.276.20
9999Mortar for laying and pointingMaterialL.S.8.062.2718.30
TOTAL
594.40
Add 1 % Water charges on “W”
5.94
TOTAL
600.34
Add GST on “X” (multiplying factor 0.2127)
127.69
TOTAL
728.03
Add 15% CPOH on “Y”
109.20
TOTAL
837.23
Add Cess @ 1% on “Z”
8.37
Cost of 10 cudm.
845.60
Cost of 1 cum.
84,560.00
Say
84,560.00

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 363. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.